RE: Are we confusing scheduling services with QSE type stuff?

From
Reagan Rorschach reagan.rorschach@enron.com
To
Kay Mann, David Fairley
Date
Thu, 31 May 2001 03:58:00 -0700 (PDT)
That means it is recognized, not  "contemplated to be recognized", then?  Is 
there such a thing as a recognized scheduling entity, or do you just schedule 
on their behalf? [Rorschach, Reagan]  SPP does not have such an entity at 
this point.  However, everyone expects this to happen sometime soon.  If this 
is causing probelms or commitments on our part because this is not even in 
existance, we should think about deleting reference to SPP rules and regs.  
Once the scope of an SPP defined scheduling entity is proferred, we can 
discuss any additional efforts required on our part to meet and be in 
compliance with that scope.


From: Reagan Rorschach/ENRON@enronXgate on 05/31/2001 10:41 AM
To: Kay Mann/Corp/Enron@Enron
cc:  

Subject: RE: Are we confusing scheduling services with QSE type stuff?


What about this?  Is this the QSE defn? [Rorschach, Reagan]  No, that would 
be Qualified Scheduling Entity that has a very lengthly ERCOT definition.  
This was greatly simplified to eliminate any confusion.  I think it is OK as 
is. 

&Scheduling Entity8 means an entity contemplated to be recognized by SPP, and 
fully qualified under SPP rules and regulations, to schedule the transmission 
of Energy, Capacity and Ancillary Services from the Facilities.


From: Reagan Rorschach/ENRON@enronXgate on 05/31/2001 07:51 AM
To: Kay Mann/Corp/Enron@Enron
cc:  

Subject: RE: Are we confusing scheduling services with QSE type stuff?

Kay, lets couch it as below...or similar....what I did below is botchy.

Reagan C. Rorschach
Enron North America
1400 Smith Street
Houston, Texas 77002
713.345.3363
Quoted or forwarded from earlier messages
-----Original Message-----
From:  Mann, Kay  
Sent: Wednesday, May 30, 2001 10:52 AM
To: Rorschach, Reagan
Subject: Are we confusing scheduling services with QSE type stuff?

(20) If and when a new RTO begins operation, seek to  [Rorschach, Reagan]  
comply with scheduling requirements and to satisfy [Rorschach, Reagan]  such 
rules and protocols [Rorschach, Reagan] that are created in [Rorschach, 
Reagan]  association therewith.