Re: TA 2000-014 - Replacement of W501F Row 3 Turbine Blades
- From
- Mitch Robinson mitch.robinson@enron.com
- To
- Ross Newlin
- Cc
- Don Miller, Kay Mann
- Bcc
- Don Miller, Kay Mann
- Date
- Thu, 2 Nov 2000 06:05:00 -0800 (PST)
Kay - What's the best way to have this covered by warranty? 9000 hours is significantly beyond the 12 month warranty period; however, since the notice occurred during the warranty period, would filing a warranty claim help cover the replacement? Ross, what is the normal recommended replacement criteria for the row 3 blades, in terms of run hours? Is it significantly more than 9000 hours? Thanks, Mitch
Quoted or forwarded from earlier messages
Ross Newlin@EES 11/02/2000 01:15 PM To: Don Miller/HOU/ECT@ECT, Mitch Robinson/Corp/Enron@Enron cc: Subject: TA 2000-014 - Replacement of W501F Row 3 Turbine Blades Don, Yet another Technical Advisory, that we just received. PLease post on Dealbench and ensure that Duke gets a copy to ascertain we are not attempting to hide anything. I plan on having some discussion with SWPC pursuant to who pays for this, can we get it done during our upcoming outage,etc to prepare for the next round of Dan Barpel questions. Ross ---------------------- Forwarded by Ross Newlin/HOU/EES on 11/02/2000 01:11 PM --------------------------- Pete McCormick@ENRON_DEVELOPMENT 11/02/2000 11:48 AM To: Ross Newlin@EES cc: Subject: TA 2000-014 - Replacement of W501F Row 3 Turbine Blades ---------------------- Forwarded by Pete McCormick/ENRON_DEVELOPMENT on 11/02/2000 11:47 AM --------------------------- Werner Robert <Robert.Werner@swpc.siemens.com> on 11/02/2000 10:36:57 AM To: "'pete.mccormick@enron.com'" <pete.mccormick@enron.com> cc: Smith Curt <Curt.Smith@swpc.siemens.com>, Shatlock Vince <Vince.Shatlock@swpc.siemens.com> Subject: TA 2000-014 - Replacement of W501F Row 3 Turbine Blades Subject: TA 2000-014 - Replacement of W501F Row 3 Turbine Blades Enron Station Shop Gleason 1 37A8046-1 Gleason 2 37A8049-1 Gleason 3 37A8009-1 Dear Mr. McCormick, Attached below is Technical Advisory 2000-014 which is applicable to the above subject unit(s). The purpose of this TA is to recommend replacement of the original W501F Row 3 turbine blades with blades of a new blade design. During the 1996-1998 time period shroud lifting and cracking has been observed on several W501F Row 3 turbine blades. The issue was attributed to high local temperatures and stresses in the Z-shroud area of the blade. Please let us know as soon as possible what your plans are relative to implementation of this Advisory. Very truly yours, <<...>> Robert Werner Quality System Operations <<TA2000-014c.doc>> <<ta00014c.pdf>> - TA2000-014c.doc - ta00014c.pdf