30 May 2001, 11:50 UTC
Re: Rigby's Proposal for Take Over LD's Section 10.3.2
- From
- Scott Dieball scott.dieball@enron.com
- To
- John G Rigby
- Date
- Wed, 30 May 2001 04:50:00 -0700 (PDT)
I took a quick stab at John's redraft of Section 10.3.2 but think we should talk further about subsections (j) -(l) in particular. John G Rigby 05/24/2001 06:15 PM To: Kay Mann/Corp/Enron@Enron, Sheila Tweed/HOU/ECT@ECT, Scott Dieball/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Bill Williams/PDX/ECT@ECT, pthompson@akllp.com cc: Subject: Rigby's Proposal for Take Over LD's Section 10.3.2 Attached is a redline against the present Take Over LD section of Rev 5 of GE world hunger. I made the changes based on what we have done in ARCOS. They are not the same because in ARCOS GE has the full testing program within their Commisssioning Period since they have the power island which is 1200 MW with the Purchaser having 24 MW for aux loads. I do not think that my new subparagraph (K) works. I have left it there to see if anyone else can tweak it and make it work. I am trying to get GE on the hook for acceleration costs that we incur and still beat the Time for Completion. We did not do that in Arcos since GE's time in theory is the same as the contractors. Probably merits an internal discussion before sharing with GE.