29 Aug 2000, 17:04 UTC
Re: LM6000 Change Order #2 - Revised
- From
- Kay Mann kay.mann@enron.com
- To
- Chris Booth
- Date
- Tue, 29 Aug 2000 10:04:00 -0700 (PDT)
Chris/Ben, We had discussed having two change orders so that the ESA stuff is easily identifiable/assignable/etc. Is this still the plan? Kay From: Chris Booth 08/29/2000 02:43 PM To: Kathleen Clark/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Kay Mann/Corp/Enron@Enron cc: Ben Jacoby/HOU/ECT@ECT, John R Ayres/NA/Enron@Enron Subject: LM6000 Change Order #2 - Revised In addition, the dual fuel cost will be split between ESA and ENA ($280,000 to ENA and $280,000 to ESA). Chris
Quoted or forwarded from earlier messages
---------------------- Forwarded by Chris Booth/NA/Enron on 08/29/2000 02:34 PM --------------------------- From: Chris Booth 08/29/2000 02:34 PM To: Kathleen Clark/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Kay Mann/Corp/Enron@Enron cc: Ben Jacoby/HOU/ECT@ECT, John R Ayres/NA/Enron@Enron Subject: LM6000 Change Order #2 - Revised Kathy and Kay, I have revised change order #2 to account for the additional scope added by ESA. Please review and comment. I did not change the effective date. For information purposes, all but item "b" are attributed to ESA. Regards, Chris