13 Nov 2001, 21:29 UTC
Construction costs of build out/sub-lease
- From
- Mark Whitt mark.whitt@enron.com
- Date
- Tue, 13 Nov 2001 13:29:59 -0800 (PST)
The following is a summary of the estimated costs of our buildout/subdivide project: Blueprints $6,000 Construction $70,000 Furniture $3,000 Voice/Data $4,000 *Commisions $16,000 *Commisions were negotiated by Enron Realty We had a profit of roughly $70,000 on the sublease over the term of the lease and will save approximately $11,000 per month on the sublease.