NEPCO Risk Identification

From
Keith Dodson keith.dodson@enron.com
To
Timothy J Detmering, Basil Karampelas
Cc
Greg Whalley, Brian Stanley, Wes Colwell, Keith Marlow, karen.barbour@enron.com
Bcc
Greg Whalley, Brian Stanley, Wes Colwell, Keith Marlow, karen.barbour@enron.com
Date
Tue, 29 May 2001 10:29:00 -0700 (PDT)
Attached is a portfolio summary of the NEPCO Project Life VAR's by the 
category of risks. I have been trying to get the VARS  summed in this order 
since we initiated this activity, but we lost our analyst and it has been a 
bit of a struggle.  The table effectively identifies the Construction Risk as 
the major risk not the Guarantees. They are interrelated and I have provided 
a comment on the connectivity.  Brian will be in Houston on Wednesday.  There 
are several issues to discuss on NEPCO.  We should likely meet with you 
and/or Basil to discuss.



Comments and clarifications:  (Thousands 000 Omitted) (Project Life Portfolio 
Summary)

Revenue  VAR ( $12,351)
This VAR is simply the interest rate risk over time

Materials / Equipment VAR ($21,700)
Calculated price risk of Procurement of Materials and Equipment over life of 
Project.  Heavily influenced by the Balance of Plant and bulks as the 
Equipment Island is normally a transfer from the owner  with minimal risk to 
NEPCO

Construction VAR ($43,896) 
This VAR represents the execution risks in engineering, construction and 
start up.  It is influenced by three elements: Definition, Productivity, and 
Timing.  Money spend can be accelerated to avoid Liquidated Damages thus the 
link to guarantees.  The sensitivity of this VAR is primarily the 
availability of  data for engineering timing plus engineering and 
construction labor price and productivity.

Schedule / Performance VAR ($26,177)
This VAR is calculated on the Performance LD's, Schedule LD's, and Aggregate 
Guarantees plus the Warranty.  Due to the timing and segregation of these 
risks, the project life VAR is not so severe.  The risks of LD's especially 
schedule LD's can be often off set by increased spending. 

Total Project VAR ($75,913)
The attachment provides only the P95 VAR, representing near worse case.  We 
also calculate the P75 VAR which is $31,212.  The credit risks of the owner 
and the five major suppliers which is not shown on the attachment must also 
be considered. It is calculated at an additional $31,162.   


An informed buyer would likely calculate the risk in NEPCO to be in range of 
$50 to $100 million and would likely discount the profit stream by this 
amount or ask us to guarantee the contracts.  
 
NEPCO has a project reserve / contingency of $75 million and a profit backlog 
of $131 million plus a warranty reserve on the books.