Enron email

Algorithmic Indexing

8 Dec 2000, 11:30 UTC

Exhibits to Enron South America Gas Turbine Purchase Agreement

From
Peter J. Thompson peterthompson@akllp.com
To
Kay Mann
Cc
lee.johnson@ss.ps.ge.com, Shoemaker, Kent (GEAE), Cheryl Lipshutz, Roseann Engeldorf, brett.r.wiggs@enron.com, Ben Jacoby, paulpipitone@akllp.com, Rob Taylor, Chris Cobb
Bcc
lee.johnson@ss.ps.ge.com, Shoemaker, Kent (GEAE), Cheryl Lipshutz, Roseann Engeldorf, brett.r.wiggs@enron.com, Ben Jacoby, paulpipitone@akllp.com, Rob Taylor, Chris Cobb
Date
Fri, 8 Dec 2000 03:30:00 -0800 (PST)
 <<Exhibits to Gas Turbine Purchase Agreement - without notations.DOC>>

This is the most recent draft of the exhibits.

The following items need to be added to complete the exhibits:

1. Exhibits B-1 and H-2 need to be added.

2. If one is warranted, a Seller Parent Guarantee should be
included as Exhibit C-1.

3. Does Exhibit F need to be updated and revised before signing?

4. In Section 3.1 of Exhibit K, the terms "Specific Date" and
"Recovery Schedule" are not defined.

5. For Exhibit T, please confirm that Enron has received all
documents that it should have received by now.

 - Exhibits to Gas Turbine Purchase Agreement - without notations.DOC