25 Aug 2000, 09:51 UTC
Electrobolt S&S Scope
- From
- Kevin Joyce kevin.joyce@enron.com
- To
- Kay Mann
- Cc
- Roseann Engeldorf, Lisa Bills, Brett Wiggs, Ben Jacoby, john.ayres@enron.com, Kent Castleman, Mary Cilia, mike.morrison@enron.com, Chris Booth
- Bcc
- Roseann Engeldorf, Lisa Bills, Brett Wiggs, Ben Jacoby, john.ayres@enron.com, Kent Castleman, Mary Cilia, mike.morrison@enron.com, Chris Booth
- Date
- Fri, 25 Aug 2000 02:51:00 -0700 (PDT)
Kay, Attached is the LM 6000 and options scope that ESA has prepared, that will be input to our MOU. It does not reflect the scope of equipment that will be procured from ABB yet; this should be forthcoming. Also below is the current cost estimate of the machines with their S&S options and the ABB scope. Please let us know what other information regarding scope that you might need. Thanks, Kevin
Quoted or forwarded from earlier messages
---------------------- Forwarded by Kevin Joyce/Corp/Enron on 08/25/2000
09:26 AM ---------------------------
From: John R Ayres on 08/24/2000 01:35 PM
To: Chris Booth/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT
cc: Brett R Wiggs/SA/Enron@Enron, Kevin Joyce/Corp/Enron@Enron, Glauco
Palhoto/SA/Enron@Enron, Gerald L Gobbi/NA/Enron@Enron
Subject: Total Electrobolt S&S Scope
Chris, attached is the total scope to S&S. From this list you should be able
to make your change order to S&S base on purchased quantities versus required
quantities. I have provided you the required quantities.
I provided you a column for the delta cost to S&S. When you are finished,
please complete the spreadsheet for all of our records. I do not know how we
are to add cost for storage either.
Thanks,
John
From: John R Ayres on 08/23/2000 12:38 PM
To: Kevin Joyce/Corp/Enron@Enron
cc: Brett R Wiggs/SA/Enron@Enron
Subject: S&S (GE) Scope of Supply Cost
Here are the total cost for the S&S scope of supply for the Electrobolt
Project. I have not included any ENA burdens or storage cost. These cost
are from purchase order with ENA to S&S.
EIGHT MACHINES EACH
The total cost of the LM 6000's, sprint package, water injection
skid = $112,855,600 or $14,106,950 each
The total cost of options (chillers stacks, cooling tower, mod. buildings,
etc. = 13,309,400 or 1,663,675 each
Totals = $
126,165,000 or $15,770,625 each
The transformers from ABB in Brazil should cost $3,200,000. total in Brazil
without shipping to the site.
Hope this helps you with the WLB bucket.
John