6 Mar 2002, 18:57 UTC
TW/ Lonestar Ward and Pecos Counties interconnect bi-directional--A-release
- From
- Mansoor Abdmoulaie mansoor.abdmoulaie@enron.com
- Bcc
- Kimberly Watson
- Date
- Wed, 6 Mar 2002 10:57:50 -0800 (PST)
The following is a level "A" cost estimate to make TW/ Lonestar existing interconnects bi-directional.
TW/ Lonestar at Ward County ( 50 to 60 mmcf/d)
According to Operations this is already bi-directional . The only things are required on this one is to take the flapper out of the check-valve
and blow down the gas in 5.33 miles of 12".
Cost of gas loss& labor = $8,000
TW/ Lonestar at Pecos County ( 100 mmcf/d)
A): TW/ Lonestar interconnect
Scope: On this one we need a bi-directional valve skid using the existing meter run.
Cost of material& labor= $ 195,000
B): Pecos Compressor Station
In order to make this interconnect bi-directional we also need to make the station ( two-compressor units) bi-directional.
Scope: Install outlet from Lonestar I/C to inlet filter with 12" piping& valves. Unit discharge would be modified to
tie in to West Texas-20"
Cost for material& labor= $ 330,000.
If you need more accurate costs ( B -release) please let me know .