Performanc stuff for you to read and comment on
- From
- Kay Mann kay.mann@enron.com
- Date
- Thu, 2 Nov 2000 03:17:00 -0800 (PST)
ARTICLE X. PERFORMANCE GUARANTEES AND ACCEPTANCE 10.1 Performance Guarantees. Seller guarantees that each Unit will meet the Performance Standards for Electrical Output, Efficiency, Water Consumption, Noise and Emissions as set forth in Section 10.2, when Performance Tests are conducted in accordance with the Performance Test Procedures. 10.2 Performance Standards. Each Unit shall meet Performance Standards as described in this Article and as set forth in the following table below in order to achieve Acceptance: 2MW Power Plants 2.4MW Power Plants 3.0 MW Power Plants Electrical Output, kW 2000 kW 2400 kW Heat Rate (LVH) 48% 48% Water Consumption 600 gal/h 620 gal/h Sound level 65 dB(A) at 100 feet 65 dB(A) at 100 feet Emissions Nox <1 ppmv <1 ppmv SOx <0.1 ppmv <0.1 ppmv CO <20 ppmv <20 ppmv VOC <20 ppmv <20 ppmv Particulates <100 mg/m3 <100 mg/m3 10.2.1 Heat Rate Guarantee. Seller guarantees that the Heat Rate as measured for each of the Units as demonstrated during the Performance Test, shall be __BTU/kWh. In the event the Heat Rate exceeds the Minimum Heat Rate Guarantee, Seller shall take all necessary actions to correct, retest the deficient Unit and cause the deficient Unit to meet the Minimum Heat Rate Guarantee. Failure to meet the Heat Rate Guarantee shall prevent Acceptance, unless Purchaser explicitly waives this guarantee in writing. 10.3.2 Electrical Output Guarantee. Seller guarantees that the Electrical Output of each Unit as demonstrated in the most recent Performance Test shall be equal or greater than 2000 kW (for a 2.0 MW Unit), 2400 kW (for a 2.4 MW) Unit, and 3000kW (for a 3.0 MW Unit). [Is this a net number? Where is it measured?] 10.3.3 Emissions Guarantee. Seller guarantees that the emissions of the [Unit] for the above listed categories when the [Unit] is operated [conditions?] 10.3.4 Water Consumption Guarantee. 10.3.5 [Sound Guarantee. Seller guarantees that the near field average A-weighted sound pressure levels of the [Unit? Facility?] shall not exceed 65dB(a) 9referenced to 20 micropascals) when measured during the Performance Test at one and a half (1.5) meters above the ground level and one (1) meter from the surface of the Equipment.] 10.3.6 Reliability. 10.4 Remedy for Failures to Meet Performance Guarantees. Except as specified in Section 10._] the failure to achieve the Performance Guarantees by the Acceptance Deadline [to be defined] shall constitute a default under this Agreement, and Purchaser shall have the remedies specified in Article []. 10.5 Testing. 10.5.1 Notice of Installation Completion; Conducting Tests. Seller shall deliver Notice to Purchaser that a Unit has achieved Installation Completion so that the Unit is ready to be tested. Within [fourteen (14) days] of receipt of this Notice, Purchaser shall perform the Performance Tests in accordance with the Performance Test Procedure; however, Purchaser shall not be required to conduct Performance Tests prior to [] days from the Delivery Date, or date of actual delivery, whichever is latest. Purchaser shall give Seller five (5) days notice of the time of the Performance Tests. Seller shall be present or to have a representative present at the Performance Tests, and shall provide technical advice during the tests; however, Purchaser may at its option conduct the test without Seller, assuming notice was properly given in accordance with this section. 10.5.2 Test Results. Performance Tests shall be conducted on a unit-by-unit basis. Upon the completion of each Performance Test Purchaser will issue a Performance Test Certificate setting forth the results achieved during such test. In the case of multiple Performance Tests on a Unit, performance shall be measured by the most recent Performance Test. 10.5.3 Costs of Retests. If one or more additional Acceptance Tests are required doe to the failure of a Unit to pass its Acceptance Test, Seller will bear the additional costs (if any) incurred by Purchaser [in excess of those costs normally associated with operating the Unit]. Such additional costs may include, but not be limited to, cost of testing, instrumentation, fuel, consumable spare parts, and additional personnel required to conduct the tests. 10.6 Acceptance. Upon the successful completion of the Performance Test for a Unit, Seller shall submit a Performance Test Certificate to Purchaser indicating that a Unit has achieved the Performance Standards and it ready for Acceptance. Purchaser shall within ten (10) days of receipt of such Performance Test Certificate, either sign such certificate acknowledging concurrence or reject such certificate specifically stating the reasons for such rejection. Acceptance for each Unit (and its associated Equipment) shall occur upon the issuance of the Performance Test Certificate by Purchaser as a result of the Unit having met the Performance Guarantees. Acceptance of the each Unit to be installed in a Facility shall occur when all of the following have occurred: (a) the issuance of a Performance Test Certificate by Purchaser as a result of a Performance Test indicating that the final Unit has met the Performance Standards; (b) all completion of training and the delivery of O & M Manuals and special tools required hereunder shall have occurred; (c) Seller has delivered to Purchaser a waiver of liens in form as shown in Exhibit-S that have been or could have been placed upon the Equipment and that there are no outstanding claims of Seller or any Vendor with respect to the Equipment for that particular Facility; (d) all of the Units in the Facility have achieved Installation Completion. [and there are no punch list items remaining to be completed.] 10.7 Obligation to Improve Performance. If the Performance Test should indicate that a Unit has met the Specific Performance Guarantees but not the Guaranteed Performance Criteria, then for a period of ninety (90) days following the Performance Test Seller shall have the obligation to use reasonable efforts to improve performance so that the Guaranteed Performance Criteria are met. Such efforts shall be at Seller,s sole cost and risk. Performance Tests shall be conducted in accordance with this Article. 10.8 Reduced Purchase Amount for Failing to Meet Guaranteed Performance Levels. Should the Performance Test of a Unit demonstrate that the Unit has met the Performance Standards except for the Electrical Output Performance Standard, the Purchase Amount related to that Unit shall be reduced by the percent by which the Unit fails to meet the Power Output/kW Performance Standard, so long as the Unit has achieved ninety percent of the guaranteed level. Seller shall within 30 days refund any prior payment received for the Unit in excess of the reduced Purchase Amount.