ERCOT Message: New South to North Line Limits

From
D Eric Smith d.smith@enron.com
To
Doug Gilbert-smith, Clint Dean, Larry Jester
Date
Thu, 24 May 2001 08:50:00 -0700 (PDT)
Here is a message that came in from ERCOT. Due to the size of the message, it 
seems to have choked the database. I will fix that problem but in the 
meantime, here is the text of the message in case it is important information 
for you guys.
;
The completion of the Limestone-Watermill 345 double circuit has made a 
significant change in the North/South interchange flows.; Previously a set of 
limits was calculated daily by ERCOT.; With the new transmission lines the 
old calculation is no longer valid.; ERCOT is now observing the South-North 
transfer as affected by the ATC calculator.; At this time we have adopted a 
set of not to exceed limits for the major 345 circuits in the transfer path.; 
These limits are:
;
Good Weather
;
Trading House-Venus 345 kv Double Circuit;;;;;;;;;;;;;;;;;;;;;;;; 1260 MVA
Jewet-Big Brown 345 kv Double Circuit;;;;;;;;;;;;;;;;;;;;;;;;;;;; 1200 MVA
Limestone-Watermill 345 kv Double Circuit;;;;;;;;;;;;;;;;;;;;;;;; 1500 MVA
;

All Bad Weather & North; 
;
Trading House-Venus 345 kv Double Circuit;;;;;;;;;;;;;;;;;;;;;;;;; 750 MVA
Jewet-Big Brown 345 kv Double Circuit;;;;;;;;;;;;;;;;;;;;;;;;;;;; 1200 MVA
Limestone-Watermill 345 kv Double Circuit;;;;;;;;;;;;;;;;;;;;;;;; 1400 MVA
;

Direct comments or questions about this posting to Lee Caylor at 512-225-7136.
;
;
;