Enron email

Algorithmic Indexing

24 Oct 2001, 20:13 UTC

FW: LINE SM-123

From
Victor Lamadrid victor.lamadrid@enron.com
To
Chuck Ames, Sandra F. Brawner, Chris Germany, Scott Goodell, John Hodge, Peter F. Keavey, Brad McKay, Jonathan Mckay, Scott Neal, Susan W. Pereira, Vladi Pimenov, Andrea Ring
and 6 more Leonidas Savvas, Maureen Smith, Craig Taylor, Judy Townsend, Victoria Versen, Frank Vickers
Cc
Kelly Loocke, Joann Collins, Steve Gillespie, Clarissa Garcia
Bcc
Kelly Loocke, Joann Collins, Steve Gillespie, Clarissa Garcia
Date
Wed, 24 Oct 2001 13:13:03 -0700 (PDT)
fyi
Quoted or forwarded from earlier messages
-----Original Message-----
From: navigator@nisource.com [mailto:navigator@nisource.com]
Sent: Wednesday, October 24, 2001 9:08 AM
To: navigator@nisource.com
Subject: LINE SM-123



                      COLUMBIA GAS TRANSMISSION CORPORATION                                 
                        NOTICE TO ALL INTERESTED PARTIES
                                OCTOBER 24, 2001

Notice ID: 3205
5 - NO RESPONSE REQUIRED                          


NOTE:  The following is being provided by Columbia as notice to all of its 
shippers of potential outages or reductions in available capacity in the 
identified portions of the system due to construction activities, routine 
maintenance, modifications, tests or repairs undertaken to protect the 
integrity and performance capability of its storage and transmission 
facilities.  The information provided below is subject to change for numerous 
reasons, including but not limited to, third-party controlled events and 
decisions, weather, work schedules, equipment availability, force majeure 
events, etc.  Thus, while Columbia is willing to provide this notice and update 
it periodically as necessary, Columbia is unable to represent and warrant that 
the specific activities will occur, or that they will occur on or near the 
specified dates. 

SUBJECT:   LINE SM-123

Due to long wall mining, effective October 26, 2001, Line 123 will be out of 
service.  Therefore, 0 non-firm capacity is available at the following receipt 
points until further notice.

The following receipt points will be affected:

   Equitable Gas:    Beaver Creek      (H1)
                     Hi Hat            (F3)

   CNR Pipeline:     Boldman           (CNR02)
                     Conoway           (CNR03)
                     Johns Creek       (CNR08)
                     Canada            (CNR09)
                     Canada            (CNR10)
                     Stafford          (CNR11)
                     Thacker/Majestic  (CNR12)
                     Briar Mtn.        (CNR13)
                     Huff Creek        (CNR14)

   Conoco:           Grant             (P1)

The same is true with respect to any Appalachian production flowing directly 
into Columbia's Line KA between Columbia's Boldman Compressor Station and 
Columbia's Huff Creek Compressor Station as well as production flowing into 
Columbia's Lines SM-116, KA-15, PM-3 and PM-17.  

If you have any questions, feel free to contact your Customer Services Team.