Rio Nogales Operation costs cap

From
Eric Gillaspie eric.gillaspie@enron.com
To
Gerald Nemec
Date
Tue, 13 Feb 2001 07:19:00 -0800 (PST)
G,

Greg and SCS recommended we put a cap in for our expenditures on operation 
costs that HPL was willing to eat for the HPL Operated Facilities.  I have 
modified section 5 accordingly for your review:

5. Operation.  RNP shall operate and maintain the RNP Facilities in 
accordance with sound and prudent natural gas industry practice and shall be 
fully responsible for the routine operation and maintenance thereof and for 
all cost and expense associated therewith.  HPL shall operate and maintain or 
cause the operation and maintenance of the HPL Facilities and the HPL 
Operated Facilities in accordance with the Standards and with sound and 
prudent natural gas pipeline industry practice and shall be fully responsible 
for the operation and maintenance thereof and for all cost, expense and risk 
associated therewith, except for any Meter Fee assessed, as defined in 
Section 3 above.   Notwithstanding the foregoing, HPL shall notify RNP five 
(5) days prior to performing any scheduled maintenance, repairs or capital 
expenditures on the HPL Operated Facilities that are in excess of $3,000.00 
for a single item for RNP,s approval, which shall not be unreasonably 
withheld.  HPL shall timely invoice RNP for such maintenance, repair or 
capital expenditures performed by HPL on the HPL Operated Facilities, and RNP 
shall pay such invoice within 15 days of its receipt thereof.    RNP shall be 
responsible for the electric power and phone service, required for the 
Interconnect.  

Eric Gillaspie
713-345-7667
Enron Building 3886