RE: GE LM-6000 purchase contract for Las Vegas Cogeneration II pr oject
- From
- lee.johnson@ss.ps.ge.com lee.johnson@ss.ps.ge.com
- Date
- Mon, 12 Mar 2001 09:17:00 -0800 (PST)
Bill/Dale/Kay- I've made redline edits with regards to LVCII performance guarantee values in Section 10.7 for output and heat rate based on the Feb 8, 2001 guarantee sheet. Dale, please send revised LVC II facility agreement to reflect Units 25-28 with appropriate schedules for price, delivery, payment and termination schedules at your earliest convenience. The units 19-20 and 23-24 that are currently reflected in this document will be left in E-Next (Turbopark). The schedules for price, delivery, payment will remain the same for these units. Thanks, Lee
Quoted or forwarded from earlier messages
-----Original Message----- From: Dale.Rasmussen@enron.com [mailto:Dale.Rasmussen@enron.com] Sent: Monday, March 12, 2001 3:03 PM To: Johnson, Lee L (PS, SSEP); Bill.Williams@enron.com; Kay.Mann@enron.com Subject: GE LM-6000 purchase contract for Las Vegas Cogeneration II project Bill Williams asked me to forward the attached execution form of the LM-6000 purchase contract. The second attachment is to be inserted as Exhibit H-2 in the contract. I understand that we received it from GE, and that it is available only in pdf format. Thanks. (See attached file: Training LM6000.pdf)(See attached file: LV Cogen Gas Turbine Purchase Agreement - Version 5.DOC) - LV Cogen Gas Turbine Purchase Agreement - Version 5_redline031201.DOC