25 Apr 2001, 23:10 UTC
Summary of the Wednesday FERC Orders
- From
- Alan Comnes alan.comnes@enron.com
- To
- Tim Belden, Mike Swerzbin, michael.driscoll@enron.com, Matt Motley, Robert Badeer, Diana Scholtes, Sean Crandall, Chris Mallory, Jeff Richter, Tom Alonso, Mark Fischer, Phillip Platter
- Date
- Wed, 25 Apr 2001 16:10:00 -0700 (PDT)
The FERC orders will not be out until sometime Thursday but here is a boiled down version of what we heard from the meeting, the press, and the press release: FERC Market Monitoring and Mitigation Plan for California ? Approved 2-1 with Massey dissenting ? Imposes mitigation (caps) in R/T in California only during Stage 1/2/3 beginning _____ (not clear; assume immediately or soon). o Applies to all thermal generation with a PGA with ISO (even if not a FERC jurisdictional entity) o All subject generation is paid a single proxy price o Proxy price is based upon the marginal unit,s gas price x heat rate + emission adder. (Heat rate determining cap will not longer be pegged at 18,000 but will change daily and posted by CAISO) o Proxy price is determined on a day-ahead basis Still not clear what gas price will be used. o Bids above the proxy are allowed but the seller must justify the cost ? Hydroelectric resources--in-state or out-of-state--are exempt. ? CAISO will still acquire resources outside of the proxy price via OOM calls ? Silent on exports and expect CAISO to cut exports unless ordered to do otherwise. (However, requirement for CAISO to become a part of a &real8 RTO would imply that it must honor firm schedules.) ? All LSE in R/T markets to submit demand bids and to identify load that can be curtailed at a specified price ? Contingent on CAISO filing a plan to become part of a region wide RTO by June 1. I.e., if CAISO does not make an adequate showing, all mitigation measures are cancelled. ? Opens an investigation on a subset of transactions. According to Massey this band is very narrow. ? The $150 breakpoint and reporting requirements, which were put into effect with the December order, will end with this order. ? In all hours (not just emergencies) there is increased market monitoring of outages and bidding behavior ? Although the plan is only for California, it seeks comments on a West-wide price mitigation plan. ? Also seeks comments on whether CAISO should impose an adder to address generator unpaid bills. RTO West: ? RTO West Phase 1 filing (made back in Nov 2000) is accepted. ? TransConnect, a Transco proposed by RTO West's transmission-owning IOUs, was also accepted. ? Incentive rates allowed if owner separates transmission from the generation. ? Phase 2 filing due December 1. This filing will require tariffs and additional details including how RTO West can become part of a larger West-wide RTO ? Order encourages Canadian utilities to be a part of RTO West