Enron email

Algorithmic Indexing

9 Nov 2001, 17:28 UTC

El Paso Maintenance on Lines 1300 and 1301 on San Juan Crossover

From
Lorna Brennan lorna.brennan@enron.com
To
Steven Harris, Lindy Donoho, Pallavi Goradia, Lorraine Lindberg, TK Lohman, Michelle Lokay, Mark McConnell, Jan Moore, Kimberly Watson, Paul Y'Barbo, Theresa Branney, Vernon Mercaldo
and 5 more Ranelle Paladino, Larry Pavlou, john.pritchard@enron.com, Preston Roobaert, Jo Williams
Date
Fri, 9 Nov 2001 09:28:57 -0800 (PST)
In its preliminary notice of November maintenance, El Paso had scheduled Lines 1300 and 1301 on the San Juan Crossover for total shutdown Nov. 29-30. It said Wednesday the shutdown has been delayed to coincide with the Dec. 1-2 weekend, when all 650 MMcf/d of the crossover's capacity will be cut to zero. Portions of Line 1300 will be shutting down Dec. 11-12 and Dec. 18-19; capacity cuts then will be 60 MMcf/d.