FW: O&M costs
- From
- Eric Gadd eric.gadd@enron.com
- Date
- Fri, 19 Oct 2001 16:09:54 -0700 (PDT)
Michael and JB, Please note for inclusion in pro-formas. Eric
Quoted or forwarded from earlier messages
-----Original Message----- From: Asante, Ben Sent: Friday, October 19, 2001 2:22 PM To: Gadd, Eric Cc: Reinecke, Bryan Subject: O&M costs Eric, The O&M costs seem reasonable. The pipe O&M is usually very very low compared to that of compression. Since the pipe is about 80% of the total capex, the composite effect the total O&M per total capital tends to be very small (1.1% in this case). Within ETS, the pipe O&M is typically $500-600/mile/year The non-fuel O&M is about $35/HP/year. If we use these benchmarks we come in lower than their estimates. Martin Donnelly has confirmed that fuel is not included in this estimate.. it is captured in the toll. Please let me know if you require further detail. ben