14 Sep 2000, 14:11 UTC
Hanover Costs
- From
- Ken Choyce ken.choyce@enron.com
- Date
- Thu, 14 Sep 2000 07:11:00 -0700 (PDT)
Shonnie/Gerald Anticipated charges from Hanover not yet received: - overtime required to monitor the Box Draw gathering system 24 hours per day because the remote alarm/SCADA system was not fully operational when the station was - cost associated with the original charge of glycol at each recip station - turbine meter repairs associated wiith start up issues (ie: weld slag in fuel gas piping) - the cost associated with air dispersion modeling for the DEQ permits - some HMS costs for their time to install telemetry instruments and debug the SCADA system Please call if you need more detail. Ken