EOTT Hunt Pipeline Update

From
Stanley Horton stanley.horton@enron.com
To
Dana Gibbs
Date
Mon, 21 May 2001 06:08:00 -0700 (PDT)
Things are not always as they seem based on further due diligence.
Quoted or forwarded from earlier messages
---------------------- Forwarded by Stanley Horton/Corp/Enron on 05/21/2001 
12:56 PM ---------------------------
From: Jerry D Martin/ENRON@enronXgate on 05/17/2001 05:31 PM
To: Stanley Horton/Corp/Enron@Enron, Phil Lowry/OTS/Enron@ENRON
cc: David Sztroin/GCO/Enron@ENRON, Jordan Hunter/ENRON@enronXgate, Dan 
Cole/Remote/Eott@Eott 

Subject: EOTT Hunt Pipeline Update

Stan & Phil ) a quick update on the status of our activities on EOTT,s Hunt 
Pipeline this week.

o On Monday, Jordan and David Sztroin drove as much of the pipeline as 
possible in preparation for Tuesday,s meeting.
o On Tuesday, Jordan, David and Dan Cole met with representatives from Boots 
Smith Construction in Laurel, MS to discuss the project.  Discussion centered 
around the pipe size (108 being the most likely), and what was included in 
the lump sum construction price from Boots Smith.
o His price did not include a number of items, such as concrete coating, 
stream crossings, wetlands installation (including mats), directional drills, 
silt fencing, and several other identified items.  He has provided, or will 
provide, unit prices for some of these items; we will estimate the balance.  
In addition, his price is for construction now, and could change if 
construction is delayed too long ) how long is not defined.
o He stated he was not interested in a total &wrap8 turnkey project.  He 
works closely with an engineering company, but did not feel comfortable doing 
the entire project, including surveying, ROW, engineering, permitting, 
procurement, etc.  His price is only for normal construction.
o On Wednesday, Jordan, David, Dan and I held a conference call.  I assured 
Dan that we would, as always, be diligent in trying to minimize cost and 
schedule while maintaining appropriate safety, quality and environmental 
parameters.

I have assigned Jordan as the Project Director for the project.  He is 
working to more clearly define the scope, standards, specifications, 
execution approach, cost and schedule.  We will advise the target schedule 
and revised cost estimate as soon as possible.  Of course, there are many 
permitting and environmental issues to overcome, and Jordan is working 
through those now; the survey needs to start ASAP in order to file for the 
permits.

Dan, if you have comments on my notes, or on the meeting, please let us 
know.  We,re looking forward to working with you.

Thanks,
Jerry