21 Jul 2000, 09:11 UTC
IOS
- From
- Susan Scott susan.scott@enron.com
- To
- Jeffery Fawcett, Steven Harris, Kevin Hyatt, TK Lohman, Michelle Lokay, Lorraine Lindberg, Christine Stokes
- Date
- Fri, 21 Jul 2000 02:11:00 -0700 (PDT)
Re paragraph 8: I just spoke with Mary Kay and Drew. Because of FERC policy on negotiated rates, we have to be careful to characterize paragraph 8 as a bid evaluation method only. Just because a shipper hits the max rate button does not mean they are committing to 100% throughput. In order to commit to 100% throughput, they need to submit a 2-part bid and indicate 100% throughput. Does this make sense? Let me know if there are any problems.