24 Oct 2001, 23:18 UTC
NPC Transmission
- From
- Mike Purcell mike.purcell@enron.com
- Date
- Wed, 24 Oct 2001 16:18:03 -0700 (PDT)
Please keep in mind when entering NPC transmission into Enpower. Beginning July 2001, the ancillary services rate for Nevada Power has been changed from $0.70 to $0.58539(roughly 59 cents) per MWh. TOTAL = $0.58539 per MWh Reserved transmission is $1.70 LLoad $2.90 HVLoad If the transmission is wheeled the .59 should be added to the reserved price and the amount entered should be: $2.29 LLoad $3.49 HVload The problems I see are deals entered at prices of $4.10, $3.60, or $2.40 or deals have been entered in at the reservation charge even though they the transmission was used. Thanks Mike P. Purcell Settlements Coordinator Volume Management-Portland 503-464-8297