8 Dec 2000, 07:39 UTC
Transco IT
- From
- Chris Germany chris.germany@enron.com
- To
- Jim Homco
- Date
- Thu, 7 Dec 2000 23:39:00 -0800 (PST)
This was the last notice about IT capacity on Transco. It was posted on the
4th at 11:22 AM.
Media Inquiries: Chris Stockton
(713) 215-2010
Other Inquiries: John McGrath 713-215-2514
December 4, 2000
To: Transcontinental Gas Pipe Line Corporation Customers and Shippers
Re: Market Area IT Availability - December 6, 2000
The available interruptible transportation service (IT and secondary FT)
on Transco for pipeline day Wednesday December 6, 2000 and continuing
until further notice is summarized as follows:
Tier I and Tier II (only Sta. 90 through Sta. 180 affected) 0 MDt/day
South Virginia Lateral Compressor Station 167 OPEN
Tier III (Station 180 through East) 0 MDt/day
Leidy - at Centerville Regulator Station (Only 50 MDt/day
Deliveries downstream of Centerville regulator affected)
Linden Regulator Station 50 MDt/day
(Located in Union County, New Jersey)
Mobile Bay Lateral 162 MDt/day
The above available interruptible transportation service refers to
deliveries into the affected area that have receipts upstream of
the bottleneck or affected area.
If you have any questions, please call John McGrath at (713) 215-2514
or Jeannette Sirois at (713) 215-2651.
J. E. McGrath
Manager
Operations Planning