8 Dec 2000, 09:14 UTC
Guardian Update--Compression Purchased
- From
- Lorna Brennan lorna.brennan@enron.com
- To
-
Margaret Carson, Julie McCoy, Steve Klimesh, gary.sova@enron.com, Rob Wilson, Lon Stanton, david.marye@enron.com, Courtney Barker, Sarabeth Smith, roger.westfall@enron.com, Steve Thomas, doug.aschwege@enron.com
and 78 more
judy.beck@enron.com, ken.anderson@enron.com, Bryan Reinecke, Robert Johnson, carolyn.descoteaux@enron.com, becki.souci@enron.com, Gary Choquette, LD Stephens, rockey.storie@enron.com, Kent Miller, John Dushinske, Dave Neubauer, Bill Fowler, Michael Bodnar, Joni Bollinger, david.badura@enron.com, Janet Bowers, Craig Buehler, Bob Burleson, allen.cohrs@enron.com, John Fiscus, Steve Gilbert, Morgan Gottsponer, Stephen Herber, Dana Jones, stephanie.korbelik@enron.com, bill.mangels@enron.com, Penny McCarran, Vernon Mercaldo, Larry Pavlou, eileen.peebles@enron.com, tony.perry@enron.com, loren.penkava@enron.com, Ken Powers, Chris Sebesta, Frank Semin, neal.shaw@enron.com, Larry Swett, Kay Threet, mike.ullom@enron.com, lisa.valley@enron.com, Chuck Wilkinson, Jim Wiltfong, Jo Williams, karen.lagerstrom@enron.com, Bob Stevens, Sue Neville, Mike Barry, Martha Janousek, Kimberly Watson, Don Powell, Steve Weller, michael.stage@enron.com, Tim Johanson, laura.lantefield@enron.com, Frank Oldenhuis, Jeff Nielsen, Robert Mason, Sean Bolks, miriam.martinez@enron.com, Lee Ferrell, John Williams, Reyna Cabrera, Theresa Branney, Jan Moore, Mike McGowan, Lynn Blair, Rick Dietz, Steven January, Sheila Nacey, Donna Scott, Dari Dornan, Maria Pavlou, Jim Talcott, Mary Kay Miller, Michel Nelson, Julia White, Drew Fossum - Date
- Fri, 8 Dec 2000 01:14:00 -0800 (PST)
Guardian Pipeline said it bought five engine compressor packages totaling 22,225 hp to provide natural gas compression on its 141-mile, 660 MMcf/d pipeline in Illinois and Wisconsin. It purchased the compressors from Compressor Systems, Inc. of Midland, TX. Combined, the compressors will be capable of delivering up to 750 MMcf/d of gas on Guardian. "Guardian Pipeline is continuing to make steady progress. This purchase agreement for a major equipment component keeps Guardian on track to meet its scheduled in-service date of November 2002," said George Hass, Guardian project manager. A final Federal Energy Regulatory Commission (FERC) decision on the Guardian Pipeline is expected by early 2001. In June, FERC issued a Preliminary Determination that the pipeline is in the public interest, subject to the outcome of its environmental review, and in July, FERC staff issued a favorable Draft Environmental Impact Statement on the project. In addition, the Public Service Commission of Wisconsin made a preliminary dete rmination on the project in October, accepting the economics of a Wisconsin Gas lateral pipeline, which will connect Guardian with Wisconsin Gas' distribution system. Guardian will transport gas from interconnections with Alliance, Northern Border, Midwestern, and NGPL at the Chicago hub near Joliet, IL, to northern Illinois and southern Wisconsin markets starting in November 2002. Its sponsors include CMS, WICOR and Viking Gas. ------------------------------------------------------------------------------ --