Brazil Power: October's Industrial Recovery and January's Rains... - CERA Alert

From
Brent Hendry brent.hendry@enron.com
Date
Wed, 23 Feb 2000 04:51:00 -0800 (PST)
FYI
Quoted or forwarded from earlier messages
---------------------- Forwarded by Brent Hendry/ENRON_DEVELOPMENT on 
23/02/2000 12:51 PM ---------------------------


Alexandre Bueno
21/02/2000 04:49 PM
To: BCC
cc:  (bcc: Brent Hendry/ENRON_DEVELOPMENT)
Subject: Brazil Power: October's Industrial Recovery and January's Rains... - 
CERA Alert


Brazil Power: October's Industrial Recovery and January's Rains... - CERA 
Alert


Brazilian power demand growth strengthened in October and November, rising 
1.8 percent and 2.6 percent, respectively, above 1998 levels for those months 
(see Figure 1). Industrial power demand led this growth, as industrial 
physical output continued to recover along with Brazil's economy. Commercial 
sector power demand growth also remained strong, but residential consumption 
increased only as a result of the addition of new billed customers, as demand 
per customer declined (see Table 1). Recent legislation to reduce the 
government's fiscal imbalances will likely continue to support Brazil's 
economic recovery, leading to higher power demand growth in the coming months.

Thermal power generation has taken on an increasing percentage of Brazil's 
total supply, substituting for hydro generation because of abnormally low 
rainfall throughout the spring months (see Table 2). Brazil's thermal 
capacity is limited, however, and hydro reserves to meet growing demand 
reached critically low levels by the end of December. The torrential rains in 
early January reduced the threat of drought-induced shortages, but by the end 
of the month reservoir stored energy levels in the South, Southeast, and 
Central West regions were only half of those in January 1999. Stored water in 
the North and Northeast regions was also significantly below the year-earlier 
level. Although hydro output has kept pace with demand and reservoir water 
levels continue to rise, the increase is much slower than historical rainy 
season buildups. Sustained rains must continue to replenish reservoir volumes 
for several months in order to eliminate the risk of power shortages.

Thermal Generation Remained High as Water Levels Stayed Low

Thermal generation continued to increase in December, reaching 1,847 
gigawatt-hours (GWh), or 6.3 percent of Brazil's total generation (see Table 
3). This increased reliance on thermal power was in response to the 
critically low reservoir water volumes resulting from Brazil's recent drought 
(see Figures 2 and 3). Although thermal generation was tapped to replace 
hydro power to the extent possible, hydro generators continued to produce 
power at levels similar to last year's in order to meet growing demand. The 
strong rains in early January reduced the threat of drought-induced 
shortages, but by the end of the month reservoir stored energy levels in the 
South, Southeast, and Central West regions fell again to only 50 percent of 
levels in January 1999, raising concerns among government regulators.

Stored water volumes in the North and Northeast regions were also 
significantly below year-earlier levels, demonstrating that Brazil's power 
capacity problem is affecting nearly all regions of the country. Brazil is 
expected to add 1,200 megawatt (MW) of new thermal capacity in 2000, as well 
as a further 1,309 MW of nuclear capacity when the Angra II unit enters 
commercial operation. This new capacity will help meet the expected increase 
in demand growth as Brazil's economy strengthens throughout the year but will 
do little to mitigate power shortages if the current rainfall is insufficient 
to replenish Brazil's reservoirs.

Industrial Activity: Recovery in October and November Boosts Power Demand

October met expectations of a gradual recovery in industrial activity. This 
trend continued to gather steam in November, pushing power demand growth to 
levels not seen since April 1998. October's industrial physical output 
expanded 1.6 percent compared with that of September and 2.5 percent compared 
with that of October 1998, reaching the highest level since September 1998. 
In November, industrial output slowed slightly, dropping 0.1 percent compared 
with October 1999, but remained 4.8 percent above November 1998 levels. Power 
demand grew accordingly, reaching 3.5 percent in October and 3.8 in November, 
making industrial power demand Brazil's fastest-growing sector for the month. 
The year-to-date contraction in industrial output continued to shrink, with 
cumulative output through November only 1.5 percent lower than the same 
period in 1998. This recovery was enough to bring year-to-date power demand 
into positive growth numbers for the first time, increasing 0.5 percent over 
J!
anuary-November 1998.

October and November brought the strongest growth to the paper, beverage, and 
transportation materials sectors, supported by improved prices in 
international markets and the start of the summer. Consumer durable goods and 
capital goods also expanded strongly in October and November, rising from 
their weak performance of the first half of the year. Year-to-date growth has 
been strongest in oil, oil product, and export-oriented sectors, whereas 
consumer durable goods and capital goods have suffered the greatest 
contraction.

On a regional basis, all states with a few exceptions showed positive growth 
in industrial output in October and November. Only the Northeast region and 
state of Bahia (still suffering from a lower level of oil industry activity) 
reported negative performance in October 1998 (2.5 and 3.2 percent, 
respectively), and Paran? was the only negative performer in November. S?o 
Paulo registered its first positive performance (1.1 percent) in the past 14 
months, and four states registered double-digit growth: Esp?rito Santo (19 
percent), Minas Gerais (13.8 percent), Ceara (11.9 percent), and Rio Grande 
do Sul (10 percent). Rio de Janeiro and Esp?rito Santo showed the strongest 
year-to-date growth, while S?o Paulo's total 1999 output remained 5.5 percent 
below that of 1998.

Part of the recent increase in year-over-year monthly output can be 
attributed to the declining production levels in 1998 as the industrial 
sector had already begun to contract by October 1998. In recent months, 
however, there has been a slow but steady growth in industrial output, led by 
a recovery in international markets for export products and an improvement in 
the economic situation. This growth is expected to continue in the coming 
months as Brazil's economy continues to strengthen.

Residential and Commercial Demand Growth Slows

Residential demand grew slowly in October and November, increasing only 0.1 
and 1.0 percent year-on-year, respectively. Even this limited growth is due 
entirely to the addition of new billable customers, which has expanded the 
customer base by 4.6 percent in the 12 months ending in November 1999. During 
that same period, per-capita power consumption declined 1.6 percent owing to 
cooler average temperatures in 1999 and a 19 percent decline in purchases of 
domestic electronic goods. The surge in consumer purchases following the Real 
Plan stabilization has now subsided, and the reduction in consumer buying 
power following the economic downturn has helped limit recent sales and use 
of electricity-intensive consumer goods.

Commercial demand grew 3.6 percent in October and 3.2 percent in November, 
slowing slightly from recent months to give year-to-date growth of 4.9 
percent in November. Much of the growth in commercial demand was due to 
internal tourism, which has benefited from the real devaluation. Increasing 
electricity intensity of new businesses has also played a role, as new 
businesses have greater electricity needs than their predecessors.

Conclusion

Although the recent rains have removed any risk of power shortages in the 
near term, reservoir water levels remain dangerously low, leading the 
government to develop an emergency thermal capacity building program. The 
current rate at which dams are being replenished is insufficient to meet the 
nation's needs within the historical rainy season. Either heavier rains or an 
extended season will be needed to avoid drought-related power outages toward 
the end of 2000. In the interim, thermal generation will remain higher than 
historical averages and new units, including Cuiaba and Angra II, will help 
increase thermal power contribution to the total generation mix.

As Brazil's economy continues to strengthen in 2000, power demand growth will 
steadily increase. This growth will be felt first in the industrial sector, 
as power demand rises with increased physical output. As consumer confidence 
and buying power increase in tandem with economic growth, commercial and 
residential power consumption will also return to precrisis levels, 
surpassing 5 percent growth.

This combination of demand growth and uncertain water supply will greatly 
increase the pressure for new generation capacity. Many risks and 
uncertainties remain, however, limiting any project's ability to reach 
financial closure. The continued delay in moving projects forward, combined 
with an additional one to two years of construction once projects are made 
viable, will further tighten Brazil's supply-demand balance in the coming 
year, regardless of the availability of water.


Full report:


http://ei-sp-data01/biblioteca/cera/la_alt_02_16_99.pdf