13 Dec 2000, 13:04 UTC
ISO's response to PX's request to remove hard cap on adjustment bids
- From
- Mary Hain mary.hain@enron.com
- To
- Tim Belden, Robert Badeer, Jeff Richter, Tim Heizenrader, Stephen Swain, Alan Comnes, Susan J Mara, James D Steffes, Christian Yoder, steve.c.hall@enron.com, Richard B Sanders, Mona L Petrochko
- Date
- Wed, 13 Dec 2000 05:04:00 -0800 (PST)
The ISO filed a response at FERC to the PX's request to remove the hard cap on adjustment bids and replace it with a floating cap that would track the price of energy in the market. The ISO opposes the proposal arguing that it may produce extremely high constrained Zonal market clearing prices in the forward markets and may be subject to the exercise of market power and to gaming. The ISO suggests the PX fix this by anchoring its Adjustment Bids (incremental and decremental bids) prices to the unconstrained market clearing price, as opposed to absolute Energy bids. In other words, the PX would establish its constrained market clearing price as the sum of the unconstrained market clearing price and the Usage Charge resulting from the ISO,s Congestion Management process. To effectuate this change, the PX would have to impose a new rule that Adjustment Bids be within $125 of the unconstrained market clearing price. The PX would then be required to process the Adjustment Bids prior to passing them on to the ISO. The PX would have to subtract the unconstrained market clearing price from each Adjustment Bid prior to submitting it to the ISO. The ISO would then utilize these Adjustment Bids, as well as those submitted by other Scheduling Coordinators, to run its Congestion Management system. After the ISO completes its Congestion Management process, the ISO would then "post-process" the Adjustment Bids (add back the unconstrained market clearing price) for use by the PX in establishing its constrained Zonal Energy prices and, as needed, by the ISO in real-time Congestion Management. The ISO says it does not intend, by presenting this alternative to the PX,s proposal, to preclude consideration of other solutions that may be presented by one or more of the utilities or by the EOB. The ISO also argued that the Commission should impose reporting requirements on those entities who submit Adjustment Bids in the ISO,s Congestion Management process. It recommends that the Commission require the submission of all Adjustment Bids to the Commission, the ISO and the EOB. It also asked the Commission to direct the PX Market Monitoring Unit, in concert with the ISO,s Department of Market Analysis, to increase its monitoring of Adjustment Bids and bids submitted in the PX forward Energy markets for evidence of the exercise of market power. The ISO argues that the effect of the FERC's December 8 Order on supply sufficiency in the ISO,s real time Imbalance Energy market was immediate and beneficial. It states the following in support. Although supply in California is still very tight, after implementation of Amendment No. 33, there were bids available in the ISO,s "BEEP Stack" to address California,s real time balancing needs for the first time in nearly a week. Immediately after the order was issued 3000 to 5000 MW of Generation internal to California and up to an additional 1990 MW of imports became available to the ISO. The following day there was only one hour in which reserves dropped below 6% and one hour in which reserves were as great as 10%. In addition, it alleges that the implementation of Amendment No. 33 has substantially relieved the burden which had previously been placed on the ISO,s operators by in-state Generators attempting to negotiate prices in real time in response to ISO Dispatch instructions. The ISO also requests that the Commission clarify its December 8 Order to confirm that sellers submitting bids above $250 in the ISO,s Imbalance Energy Market are required to report their bids and provide cost information on a weekly basis not only to the Commission, but also to the California Electricity Oversight Board and the ISO. The ISO requests clarification that the Commission intended to approve the proposed December 12, 2000 effective date for the cost allocation elements of Amendment No. 33.