27 Oct 2000, 07:39 UTC
Revision No.1 for ENA Fuelcell Estimate dated 10/26/2000
- From
- Scott Healy scott.healy@enron.com
- Date
- Fri, 27 Oct 2000 00:39:00 -0700 (PDT)
FYI.
Quoted or forwarded from earlier messages
---------------------- Forwarded by Scott Healy/HOU/ECT on 10/27/2000 07:40
AM ---------------------------
Michael D Nanny@ENRON_DEVELOPMENT
10/26/2000 04:33 PM
To: Scott Healy/HOU/ECT@ECT, Stephen Plauche/Corp/Enron@Enron
cc: Robert P Virgo/HOU/ECT@ECT
Subject: Revision No.1 for ENA Fuelcell Estimate dated 10/26/2000
---------------------- Forwarded by Michael D Nanny/ENRON_DEVELOPMENT on
10/26/2000 04:25 PM ---------------------------
Ray Danner@ENRON
10/26/2000 03:44 PM
To: Michael D Nanny/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Mike
Coleman/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Terri
Austin/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT
cc: Jay Patel/ENRON_DEVELOPMENT@ENRON_DEVELOPMENt, Robin Long/NA/Enron@ENRON
Subject: Revision No.1 for ENA Fuelcell Estimate dated 10/26/2000
Mike,
Attached are the revised (Revision 1) BOP Estimates for the Wallingford Fuel
Cells Power Project (10 cells - 21.2 MW) and the Midcon (Hartford) Fuel Cells
Power Project (12 cells - 28.8 MW) in the amount of $9.5MM and $9.6 MM
respectively. These estimates reflect our discussions today with the
following comments provided:
1. I have lowered the Contingency to 10% from 15% per the direction from
Mike Coleman. Estimating does not agree with this reduced contingency and I
feel it is inadequate for the level of detail provided.
2. Because of this reduction in contingency, I have re-evaluated the
concrete account and moved the Slab on Grade from the FCE Scope to the EE&CC
Scope of Work. I have also revised the foundations for FCE based on the
quantities they provided.
3. We are using $10,000 per cell for Grounding Grid based on reviewing
additional estimating data. (The earlier number of $75,000 for the first two
(2) cells and $25,000 for each additional cell was provided as an estimate
from FCE. We agree it is too high.
4. Based on our discussions, we are using $450,000 per project for
Engineering Services.
A Basis of Estimate is also provided.
Please call if you have questions or if you want to have additional meetings.
Ray Danner
---------------------- Forwarded by Ray Danner/NA/Enron on 10/26/2000 03:26
PM ---------------------------
From: Jay Patel@ENRON_DEVELOPMENT on 10/26/2000 03:24 PM
To: Ray Danner/NA/Enron@Enron
cc:
Subject: Revision No.1 for ENA Fuelcell Estimate dated 10/26/2000
Ray, herewith, please find the subject Estimate and respective Basis of
Estimate.
Regards
Jay N. Patel
X-55262