28 Feb 2000, 09:30 UTC
Re: Calpine Indicative Pricing
- From
- Jinsung Myung jinsung.myung@enron.com
- To
- Scott Healy
- Date
- Mon, 28 Feb 2000 01:30:00 -0800 (PST)
Scott: Please see below.
1. How much would this pricing change if power could be called ion 4 hour
blocks and the availability percentages were 97%?
- 4 hour block call: There is a possibility to get better pricing.
- 97% availability: Structuring wants to make sure that there is no
regulatory limitation in related to environmental issue, which may prevent
97% availability.
2. What pricing does the 20 year project model show that we need?
- We also need power curve from year 3 to 20 to calculate Calpine's merchant
revenue.
- We are currently refining the model regarding IDC, residual value, etc.
3. What additional information do you need from me to complete your analysis?
- Unit contingency or liquidated damage protection
- Exact location for power and gas
Once we find out unit contingency and location, I will get the pricing with a
couple of scenarios as you asked:
- Flat and annual capacity for 3 and 5 year
- Power curve from year 3 to 20
Jinsung
From: Scott Healy @ ECT 02/28/2000 07:53 AM
To: Jinsung Myung/Corp/Enron@ENRON
cc: Mike J Miller/HOU/ECT@ECT
Subject: Re: Calpine Indicative Pricing
1. How much would this pricing change if power could be called ion 4 hour
blocks and the availability percentages were 97%?
2. What pricing does the 20 year project model show that we need?
3. What additional information do you need from me to complete your analysis?