FERC Issues Draft Environmental Impact Statement on Guardian Pipeline
- From
- Lorna Brennan lorna.brennan@enron.com
- To
-
Julie McCoy, Steve Klimesh, Sarabeth Smith, gary.sova@enron.com, Rob Wilson, Lon Stanton, kristen.hand@enron.com, Keith Petersen, Michele Winckowski, Donna Martens, Josie Call, bret.fritch@enron.com
and 94 more
Donald Vignaroli, roger.westfall@enron.com, Steve Thomas, doug.aschwege@enron.com, judy.beck@enron.com, ken.anderson@enron.com, Bryan Reinecke, Robert Johnson, carolyn.descoteaux@enron.com, becki.souci@enron.com, Gary Choquette, LD Stephens, John Goodpasture, Michael Ratner, rockey.storie@enron.com, Kent Miller, John Dushinske, Dave Neubauer, Michael Bodnar, Joni Bollinger, david.badura@enron.com, Janet Bowers, Craig Buehler, Bob Burleson, allen.cohrs@enron.com, John Fiscus, Steve Gilbert, Morgan Gottsponer, james.harvey@enron.com, Stephen Herber, Dana Jones, stephanie.korbelik@enron.com, bill.mangels@enron.com, Penny McCarran, Vernon Mercaldo, Larry Pavlou, eileen.peebles@enron.com, tony.perry@enron.com, loren.penkava@enron.com, Ken Powers, Chris Sebesta, Frank Semin, neal.shaw@enron.com, Larry Swett, Kay Threet, mike.ullom@enron.com, lisa.valley@enron.com, Chuck Wilkinson, Jim Wiltfong, Jo Williams, karen.lagerstrom@enron.com, Ray Stelly, Bob Stevens, Sue Neville, Mike Barry, Martha Janousek, Kimberly Watson, Don Powell, Steve Weller, michael.stage@enron.com, Tim Johanson, laura.lantefield@enron.com, Frank Oldenhuis, Jeff Nielsen, tracy.schwartzkopf@enron.com, Robert Mason, Sean Bolks, miriam.martinez@enron.com, Lynn Blair, Rick Dietz, Steven January, Sheila Nacey, Dari Dornan, Maria Pavlou, Jim Talcott, Mary Kay Miller, Michel Nelson, Mike McGowan, Julia White, Drew Fossum, Glen Hass, Mary Darveaux, Rita Bianchi, Ranelle Paladino, Steven Harris, Jeffery Fawcett, Lorraine Lindberg, Kevin Hyatt, Christine Stokes, TK Lohman, Michelle Lokay, Lindy Donoho, Lee Huber, Susan M Scott - Date
- Wed, 12 Jul 2000 07:09:00 -0700 (PDT)
FERC Staff Issues Favorable Draft Environmental Impact Statement on
Guardian Pipeline
The FERC Staff has issued a Draft Environmental Impact Statement
determining that construction of Guardian Pipeline would have limited
environmental impact and would be an environmentally acceptable
action, based on its proposed and other mitigation measures. The
Draft covers the environmental aspects of constructing and operating
the 149-mile Guardian Pipeline. FERC will take written public
comments on the Draft until August 28th, and will conduct four public
meetings along Guardian's route starting August 14th. It will
address
the comments before issuing a final Environmental Impact Statement on
the project. A final decision on the Guardian Pipeline expected early
next year. The Guardian Pipeline will transport volumes from
interconnections with Alliance, Northern Border, Midwestern Gas
Transmission, and NGPL at the Chicago hub to northern Illinois and
southern Wisconsin markets. The project will consist of a 25,000
horsepower of compression and 141 miles of 36 inch pipeline extending
from Joliet to the Ixonia, WI, with an additional 8.5 miles of 16
inch pipeline extending from the main Guardian line to near Eagle,
WI.