Contract Approval, AFE's and Consulting Arrangements

From
Dana Gibbs dana.gibbs@enron.com
To
regional.managers@enron.com, Susan Ralph, jim.parmer@enron.com, Joe Richards, Stanley Horton, Bob Jacobs, Jon Trevelise, Lori Maddox, Cutty Cunningham, Mary Ellen Coombe, David Hultsman, brent.brown@enron.com
and 2 more steve.myers@enron.com, Steve Duffy
Date
Thu, 20 Jul 2000 07:43:00 -0700 (PDT)
FROM:??????????? Dana Gibbs
 
DATE: ??????????? July 19, 2000
 
RE:?????????????????? Contract Approval, AFEs and Consulting Arrangements

??????????? The following guidelines must be followed for all existing 
projects, as well as new contracts, AFEs and consulting arrangements.? 
 Contract Approval
??????????? Effective immediately, all contracts must be approved by legal, 
with the final version of the contract initialed by legal prior to 
execution.? Exceptions will be limited to the execution of crude oil 
purchases and sales contracts that are on a pre-approved form and occur in 
the normal course of business.? Any other exceptions must be approved by the 
Office of the Chairman.? In order to ensure that we have a handle on existing 
contracts, please provide a copy of any finalized contract which legal did 
not initial prior to execution, but is currently in effect or not yet 
performed, to Molly Sample by July 25, 2000.? 
AFEs
??????????? Based on my review of the latest AFE report, EOTT needs to 
utilize this tool to better manage all of its expenditures for budget 
purposes to ensure proper prioritization of EOTT's cash.? Company policy 
requires that all expenditures greater than $5,000 that relate to expansion 
capital and maintenance capital are required to have an AFE set up prior to 
any expenditure.? I have asked the property accounting group to monitor 
compliance with that policy starting today and hold for payment any 
expenditures not authorized according to the policy.? Effective immediately, 
all employees will be prohibited from starting any project that does not have 
an approved and signed AFE.? In addition to ensuring that the current policy 
is strictly adhered to, the policy will be broadened to include a) 
expenditures for environmental expenses captured on the EMS Works system and 
b) the use of blanket AFEs for small recurring asset purchases such as 
computer equipment (computer equipment under $5,000 would be capitalized 
under these blanket AFEs and no longer expensed).? 
??????????? In order to more accurately monitor existing AFEs, please be sure 
the following steps are taken for each AFE prepared by your department:? 1) 
obtain competitive bids prior to starting a project; 2) all projects for 
which costs are projected to exceed the approved AFE by 10% or $50,000, 
whichever is less, must have a supplemental AFE prepared and submitted for 
approval within 30 days of the projected budget overrun, and 3) any project 
that is in process and does not have an AFE must be put on hold until an AFE 
can be approved, and 4) any open AFEs that are fully completed (meaning all 
invoices have been received and routed for payment) must be closed.? A final 
capital and maintenance budget for all authorized (and still open) AFEs will 
be completed and distributed by July 25, 2000.
 ??????????? Please consult Joe Richards for information necessary to utilize 
the AFE System for all future AFE processing or for a copy of the AFE policy.
 Consulting Contracts and Service Contracts
 ??????????? Effective immediately, no new consulting arrangements may be 
entered into or extended without the approval of the Office of the Chairman.? 
Additionally, Human Resources/Administration must be contacted prior to 
entering into any consulting arrangements to 1) arrange for office space, if 
necessary for the project, and 2) to determine how the position should be 
filled (contract position, temporary employee, or permanent employee).? For 
all existing consulting agreements, please provide me with a comprehensive 
listing by arrangement, including terms and business rationale, by July 25, 
2000.? Please contact Molly Sample to prepare a contract for any undocumented 
consulting arrangements.? Written documentation on all consulting/contracting 
arrangements must be maintained by Human Resources in the event of any 
governmental agency audit of EOTT's contract employees. 
 ??????????? Contractors who provide various services, such as trucking, 
environmental cleanup, maintenance, etc. must execute a service contract and 
maintain a valid insurance certificate to remain on EOTT's approved 
contractor list, which is available on EOTT's Intranet.? Requests for service 
contractors must be sent to John Zimmerman in the Legal Department.? Please 
forward a request for contract to John for any service arrangements which are 
not documented by July 25, 2000.

Accounts Payable Documentation
??????????? Please be reminded that the Accounts Payable Department requires 
complete and timely documentation for all invoices submitted for payment.? 
This includes all charges made using a P card.? Incomplete invoices or copies 
of invoices will be returned to the submitting party.? For service contracts, 
a summary of hours, hourly rate, and a brief description of the work 
performed by person, by date, and by project, along with documentation to 
support specific authorized out-of-pocket expenses, must be submitted before 
payment can be made.? For materials, a comprehensive description of all 
items, including the quantity purchased, must be submitted before payment can 
be made.? 
 
??????????? Please notify the appropriate people in your respective 
departments of these procedures and contact me if you have any questions or 
comments.