TW/ Lonestar Ward County intercoonect-----Level-A cost

From
Mansoor Abdmoulaie mansoor.abdmoulaie@enron.com
To
Michelle Lokay
Date
Thu, 21 Feb 2002 09:30:23 -0800 (PST)


Michelle

In order to make this interconnect bi-directional the following work need to be performed: 
( capacity 35- 60 mmcf/d at 800-850 # pressure)

1):  Blowdown gas in 5.335 miles of 12" ( gas-loss) at 1000# pressure

2):	Remove a flapper in the check-valve or turn around the existing check-valve


The  cost for this is approximately $8,000 to $10,000.

Still waiting for Earl Chanley from Roswell to send me some facility information regarding the Pecos interconnect.

Mansoor