12 Sep 2001, 15:42 UTC
TW-Blanco Hub and Questar interconnect 80-120 mmcf/d
- From
- Mansoor Abdmoulaie mansoor.abdmoulaie@enron.com
- Date
- Wed, 12 Sep 2001 08:42:00 -0700 (PDT)
Kim The level "A" (30% ?) to construct a new interconnect between TW and Questar at suction side of San Juan are as follows: Facility requirements: Tap/ Side-valve ( $75,000) 12" Ultra-Sonic meter Flow control-valve with positive shut-in Install fence-site Meter Building Chromatograph EFM& SCADA Costs: Material costs: $240,000 Contact, inspection $135,000 Eng and project management Contingency $50,000 OH and AFUDC $20,000 Total $520,000 If you have any questions please call. Mansoor