TW-Blanco Hub and Questar interconnect 80-120 mmcf/d

From
Mansoor Abdmoulaie mansoor.abdmoulaie@enron.com
To
Kimberly Watson
Date
Wed, 12 Sep 2001 08:42:00 -0700 (PDT)
Kim

The level "A" (30% ?) to construct a new interconnect between TW and  Questar at suction side of San Juan are as follows:

Facility requirements:

Tap/ Side-valve	( $75,000)
12" Ultra-Sonic meter
Flow control-valve with positive shut-in
Install fence-site
Meter Building
Chromatograph
EFM& SCADA

Costs:

Material costs:			$240,000
Contact, inspection		$135,000
Eng and project management
Contingency			$50,000
OH and AFUDC			$20,000	

Total				$520,000

If you have any questions please call. 



Mansoor