16 Feb 2001, 17:50 UTC
Information Management Weekly Milestones Report
- From
- Marie Hejka marie.hejka@enron.com
- Cc
- Beth Perlman, Steven J Kean, Rick Buy, Richard Causey, Cindy Olson, Philippe A Bibi, Karina Prizont, Maureen McVicker, Sharron Westbrook, Peggy McCurley, Karen K Heathman, Kathy McMahon
- Bcc
- Beth Perlman, Steven J Kean, Rick Buy, Richard Causey, Cindy Olson, Philippe A Bibi, Karina Prizont, Maureen McVicker, Sharron Westbrook, Peggy McCurley, Karen K Heathman, Kathy McMahon
- Date
- Fri, 16 Feb 2001 09:50:00 -0800 (PST)
Information Management Weekly Milestones Report ) 02/16/01 General Project Status. Project continues on schedule. An IM executive sponsor meeting is scheduled for 2/23/01, 2:00 - 3:00 p.m., EB50M03. All IM executive sponsors have been confirmed to attend. Portal. Brandon Rigney's team has completed and presented the portal "Look and Feel" to the portal IT team. Steve Kean will be presented this next week. The portal "Look and Feel" meets Corp. marketing and communications guidelines and specifications. Brandon's team is recommending the portal name: anywhere.enron.com. Price-Waterhouse demonstrated Hewlitt Packard's benchmark portal. Before this portal, HP had 9000 webpages and some 300 competing channels. They consolidated their webpages down to 900. Now they have one portal with a host of seamless applications available through a single sign-on process. Approximately 90% of employees use this tool. The portal was unveiled in October of 2000. The $30 million project costs were realized by February, 2001. In cost savings, HR alone has saved $10 million since October, 2000. PW's portal uses both Verity and Infoseek as their search engines. The task force will work with PW contacts at HP to learn about their experience with both these tools. Allan Sommer has targeted resources to support the change management initiative for the portal pilot. According to HP the key to success for a portal project is change management. Communicate, communicate, communicate. Joe Wong's development team continues portal pilot development. All potential portal pilot applications (in scope, out of scope, and killer applications) are being reviewed for delivery. UDM/ESE. Verity has been selected as the UDM/ESE tool of choice to pilot. Sue Vasan has been identified as the internal Business Analysts/Project Coordinator for the UDM/ESE pilot. Sue, who works for Debbie Brackett in Rick Buy's organization, will be working this pilot effort for the next three weeks minimum. All task force members are to identify targeted audiences to test the UDM/ESE tool. All task force members are to identify a list of BU/FU applications to target a UDM/ESE tool to search on (e.g. LiveLink, HR systems, etc.). IM Strategy Proposal. Per Steve Kean, the Task Force should continue focusing on delivering our objectives with little expense tagged to this project. Task force members are encouraged to provide resources and support for all task force initiatives. Allan Sommer is scheduled to deliver a draft of the IM Strategy Proposal. Allan will deliver his pre-draft work to Marie Hejka end of week.