NYPSC approves market-based backout credit for RG&E; Adopts Enron Online as Index
- From
- Howard Fromer howard.fromer@enron.com
- To
-
jeffery.ader@enron.com, Michael R Brown, Mark Dana Davis, tom.dutta@enron.com, John Suarez, Doug Sewell, Richard Ring, Charles Decker, gary.keevill@enron.com, John Llodra, Tom May, Pearce W Hammond
and 18 more
Christi L Nicolay, Sarah Novosel, Dan Staines, W David Duran, Richard Lydecker, Steve Montovano, James D Steffes, Janelle Scheuer, rick.bachmeier@enron.com, lance.hinrichs@enron.com, Jim Meyn, berney.aucoin@enron.com, Richard Shapiro, patricia.collins@enron.com, Fatimata Liamidi, dag.joraholmen@enron.com, dwight.fruge@enron.com, john.campbell@enron.com - Date
- Mon, 2 Apr 2001 10:38:00 -0700 (PDT)
Another big victory for Enron in New York! In an Order issued by the NYPSC on March 29, the NYPSC has approved a proposal to modify the existing fixed backout credit of 2.8 cents per kwh for energy and capacity and replace it with a market-based backout credit. The additional retail adder of 0.4 cents per kwh would remain. Load-serving entities (LSEs) will have the option of continuing to buy their energy and capacity from RG&E at the market based backout credit which will be determined 15 days prior to the beginning of each of the two six-month capability periods, and will be based on "a forecast of energy prices derived from Enron Corporation's (Enron) EnronOnline trading platform." To my knowledge, this is the first occasion that a regulatory body has agreed to use Enron Online as an index! LSEs can elect instead to procure their own commodity and get a market-based backout credit (MBBC). Under this option, the LSEs will get a market based backout credit. However, the Enron online prices for the six months determined as above will be reconciled on a lag basis against actual market prices. The PSC has capped the amount of the reconciliation for any LSE to the product of the LSE's total load for the calendar year and $0.065 per kwh (PSC staff's estimate of RG&E's embedded power supply cost). (The PSC Order actually says $0.015 but this appears to be a mistake since the attached settlement states $0.065.) A copy of the PSC's Order is available on its website: www.dps.state.ny.us