Randy, based upon the records review, this is the only issue that may be a problem. If a tank has been moved to another location, it would trigger requirements which were enacted on the date of the relocation. For instance, if a tank constructed prior to 1973 was moved in 1978, there would be emissions control requirements placed on the tank as required by the 1978 tank regulations. If the tank had remained at its original location, it would be grandfathered with respect to emissions. However, because the tank was relocated, it is looked upon as being a tank constructed in 1978 and subject to the 1978 regulations and is no longer grandfathered. I was not given this information during the records review, so I dont know if any of the tanks apply. If any of the tanks fit into the above scenerio, EOTT or Koch will be looking at some major $$$$$ to bring any subject tank into compliance. Generally speaking, the regualtions and costs to comply increase as a function of date. 1. Q. Of the tanks listed on the spreadsheet, have any of the tanks been relocated from its original construction locations? List the tank, date moved and location moved to. A. Benevides Station Tank 6125 and Mirando Station Tank 28591 were relocated to those stations. Three Rivers Tanks 28508 and 28100 were relocated and re-erected at that station. Duval Station Tank 28052 and Mirando Station 28045 were relocated and re-erected at those stations prior to Koch,s acquisition of those assets.
Quoted or forwarded from earlier messages
---------------------- Forwarded by Larry Campbell/ET&S/Enron on 05/09/2001 10:03 AM --------------------------- Jim Coen @ EOTT 05/08/2001 10:27 AM To: Joe Richards/Houston/Eott@Eott, Randy Belyeu/OTS/Enron@ENRON, Larry Campbell/ET&S/Enron@Enron, Warren Fusilier/Remote/Eott@Eott, Jeremy Dawson/Houston/Eott@Eott cc: Subject: Koch South Texas pipeline data room questions and answers ----- Forwarded by Jim Coen/Houston/Eott on 05/08/2001 10:51 AM ----- "Lofing, Michael" <LofingM@kochind.com> 05/08/2001 09:48 AM To: Jim Coen/Houston/Eott@Eott cc: Subject: Koch South Texas pipeline data room questions and answers Jim Attached are the Koch South Texas Pipeline data room questions with answers attached. I have also attached data provided to other bidders. If you have any additional questions, please contact me, 828-4027. Regards, Mike <<EOTT Questions and Answers_.doc>> <<over-short labor utilities.xls>> <<CrudeVehicles.xls>> - EOTT Questions and Answers_.doc - over-short labor utilities.xls - CrudeVehicles.xls