with:wood@enron.com means wood@enron.com.
-
26 Oct 2001
Medicine Bow Tie-In Capacity
Dear Medicine Bow Shipper: We received notification that the 5th segment to gate valve 6 providing a total firm capacity of 495 Mdth/day was approved by FERC today. Based…
-
18 Oct 2001
Laine Lobban to connie.schenderlein@williams.com, wayne.ellis@williams.com, kelly.knowlton@williams.com and 78 more
Medicine Bow Tie-In Capacity
Dear Medicine Bow Shipper: Yesterday, we filed with FERC for approval of the fifth tie-in segment (to gate #6) contracted for 115 Mdth/day. This will bring the firm capac…
-
18 Oct 2001
Michael Murphy to murphy@enron.com, Michael Murphy, electric4@coned.com and 46 more
RE: Cycle Usage Files
Please note the correction below. Thanks, Michael Murphy Consolidated Edison Company of New York Retail Choice Operations (212) 780 6723
-
18 Oct 2001
Michael Murphy to electric4@coned.com and 46 more
Cycle Usage Files
Due to technical problems,. Cycle Usage files were delayed in posting to the Retail Access Web Site. Later this morning a file will be posted, containing cycle usage info…
-
17 Oct 2001
Hudson, Todd" @ENRON to todd.hudson@enron.com and 16 more
RE: Pipeline Interconnect Forum - Sunday Event Schedule
One more note: Casual dress is appropriate for Sunday. Todd Hudson Information Systems Analyst Gas System Operations 415.973.1386
-
17 Oct 2001
Michael Murphy to electric4@coned.com and 50 more
Retail Access Cycle Usage Files
Due to technical problems the posting of the 10/16/01 cycle usage files on the Retail Access internet site will be delayed until midnight tonight 10/17/01. Please contact…
-
17 Oct 2001
RE: Pipeline Interconnect Forum - Sunday Event Schedule
Folks, We are working with the hotel to have walking maps provided for you with directions from the hotel to the restaurant. For those of you that will be coming from oth…
-
15 Oct 2001
Laine Lobban to connie.schenderlein@williams.com, wayne.ellis@williams.com, kelly.knowlton@williams.com and 78 more
Medicine Bow Tie-In Capacity
Dear Medicine Bow Shipper: This morning we received FERC approval for the fourth tie-in segment (to gate #7) contracted for 92 Mdth/day. This brings the firm capacity of …
-
10 Oct 2001
Laine Lobban to connie.schenderlein@williams.com, wayne.ellis@williams.com, kelly.knowlton@williams.com and 74 more
Medicine Bow Tie-In Capacity
Dear Medicine Bow Shipper: This morning we received FERC approval for the third tie-in segment (to gate #8) contracted for 79 Mdth/day. The contract effective date will b…
-
2 Oct 2001
Hudson, Todd" @ENRON to Lynn Blair and 20 more
Pipeline Interconnect Forum - Sunday Event Schedule
This email is intended for those Forum participants who have confirmed for the Sunday kickoff event. Lunch will be starting at 1 pm. You will need to travel from the hote…