    Permits: Interconnection: Easier for EPMI/EES to purchase from industrials

    To alert you to another item that may arise: Some industrials have air permits that restrict them to running for self-supply backup generation only. In such case, the air…

  2. 14 May 2001

    Christi L Nicolay to Chris Lackey, Christopher F Calger, Tim Belden and 104 more

    Permits: Interconnection: Easier for EPMI/EES to purchase from industrials

    To alert you to another item that may arise: Some industrials have air permits that restrict them to running for self-supply backup generation only. In such case, the air…

  3. 1 May 2001

    Christi L Nicolay to Chris Lackey, Christopher F Calger, Tim Belden and 103 more

    Interconnection: Easier for EPMI/EES to purchase from industrials

    Please note that with the authorization below, interconnection issues with the attached utility still need to be addressed. (This includes agreement, queue, facilities if…

  4. 1 May 2001

    Christi L Nicolay to Chris Lackey, Christopher F Calger, Tim Belden and 103 more

    Interconnection: Easier for EPMI/EES to purchase from industrials

    Please note that with the authorization below, interconnection issues with the attached utility still need to be addressed. (This includes agreement, queue, facilities if…

  5. 1 May 2001

    Christi L Nicolay to Ozzie Pagan, Heather Kroll, David Fairley and 37 more

    SPP REHEARING

    Attached below is EPMI's request to FERC for clarification that SPP should not proceed with spending $45 million to implement a market design until FERC approves SPP as a…

  6. 1 May 2001

    Christi L Nicolay to Chris Lackey, Christopher F Calger, Tim Belden and 104 more

    Easier for EPMI/EES to purchase from industrials

    Attached is FERC authorization for EPMI and EES to purchase power from industrials NATIONWIDE (effective March 6, 2001--Does not expire). The industrial does not have to …