27 Sep 2001
Duong Luu to Cara Semperger and 10 more
Re: Testing the PSW
Hello Cara, Please see comments showing below in RED BTW, if you need me to unroute all daily route & term route for June 22, i will be happy to do so. Thanks for taking …
-
25 Sep 2001
Duong Luu to Corry Bentley, Cara Semperger, asem@enron.com and 3 more
RE: Testing the PSW
Thanks Cara & Corry, i will make sure every item get resolved dluu
-
25 Sep 2001
Corry Bentley to Cara Semperger, asem@enron.com, David Poston and 4 more
RE: Testing the PSW
I ran the PSW for the East (6/22 data) and also had problems with each of the following: 1) Enter moves cell to the left 2) Colors changed 3) Path with transmission did n…
-
12 Sep 2001
Will Smith to Corry Bentley, Asem Atta, Vishwanatha Venkataswami and 2 more
RE:
Corry, Asem is out today. I have Vish looking into it. Will
-
10 Sep 2001
Asem Atta to Corry Bentley, Cara Semperger and 8 more
Preschedule Workspace
A new version of Preschedule Workspace has been migrated to Stage addressing the 'EDIT' bug of copying workspace. regards, Asem Atta x31700 Enron Net Works
-
10 Sep 2001
Asem Atta to Corry Bentley, Will Smith and 6 more
RE: PSW/PSC 0910 Test
Corry, As per Will, the understanding was that deals with transmissions were far and few in between and were currently being manually routed, and this was not a feature t…
-
10 Sep 2001
Corry Bentley to Will Smith and 4 more
PSW/PSC 0910 Test
Will, I found about the same issues we had already discussed while running the PSW/PSC. I ran the sheet for 6/19 since there were no "West" paths in the confirmations (I …
-
7 Sep 2001
Asem Atta to Cara Semperger, Corry Bentley, David Poston and 4 more
RE: Status Report and Production Release Note
Just got done talking with Corry, and Deal Scheduling showing the incorrect status of a physical routed flag is an issue. Corry will proceed and test against pwrtestp on …
-
6 Sep 2001
Asem Atta to Cara Semperger, Corry Bentley and 8 more
RE: Testing PSW and Path confirmation for Target date 6/20
Cara, Thanks for stepping me through Deal Scheduling to see exactly what the problem was in regards to the Physical/Non-Physical issue. Addressed this issue and we have s…
-
6 Sep 2001
Asem Atta to Cara Semperger, Corry Bentley and 8 more
RE: Testing PSW and Path confirmation for Target date 6/20
Cara et all, Following list of bug fixes are moving out to stage to address the recently reported issues: New versions of both applications have been moved out to stage..…
-
5 Sep 2001
Cara Semperger to Asem Atta, Corry Bentley, David Poston and 8 more
Testing PSW and Path confirmation for Target date 6/20
Good Morning/Afternoon/Evening; I started working in June 22 to test path cut capabilities. I was able to save a cut path. Please make sure that Bill Williams III and Who…
-
5 Sep 2001
Asem Atta to Cara Semperger and 8 more
RE: Testing the PSW and Path Confirm Report
Cara, Could I get a copy of the psc file for the preschedworkspace tests you ran today? Id like to mimic your actions to see exactly how these errors were generated and p…
-
5 Sep 2001
Cara Semperger to Asem Atta, Corry Bentley, David Poston and 8 more
Testing the PSW and Path Confirm Report
Good Morning/Afternoon/Evening; I started working in June 22 to test path cut capabilities. I was able to save a cut path. Please make sure that Bill Williams III and Who…