  1. 28 Mar 2001

    Zhiyong Wei to Louise Kitchen and 10 more

    GTV II weekly status update

    Louise, The GTV II team has a weekly status meeting on Mondays. Yesterday, we had our first status meeting. Please see below for the current status of the project. Please…

  2. 27 Mar 2001

    Louise Kitchen to Zhiyong Wei and 10 more

    GTVII

    Zhiyong Thanks for getting me the signed (so far) copy. (Beth and Philippe, please sign the document today ). When they have signed please recirculate the final signed co…

  3. 27 Mar 2001

    Zhiyong Wei to Louise Kitchen and 10 more

    GTV II weekly status update

    Louise, The GTV II team has a weekly status meeting on Mondays. Yesterday, we had our first status meeting. Please see below for the current status of the project. Please…

  4. 27 Mar 2001

    Louise Kitchen to Zhiyong Wei and 10 more

    GTVII

    Zhiyong Thanks for getting me the signed (so far) copy. (Beth and Philippe, please sign the document today ). When they have signed please recirculate the final signed co…

  5. 22 Mar 2001

    Zhiyong Wei to Louise Kitchen and 2 more

    RE: GTV II update

    Louise, An update. Dave Nommensen signed the document. Regards Zhiyong

  6. 22 Mar 2001

    Zhiyong Wei to Louise Kitchen and 2 more

    GTV II update

    Louise, I would like to give you an update of GTV II inception document. I have obtained the signatures from most people on the sign-off sheet except Colleen Sullivan, Ph…

  7. 20 Mar 2001

    Zhiyong Wei to Louise Kitchen and 10 more

    RE: GTV II

    Please see the attached file for the revised inception document. I would appreciate any comments. We will be working on the specification of phase 2 once this document is…

  8. 19 Mar 2001

    Louise Kitchen to Zhiyong Wei and 10 more

    RE: GTV II

    Comments: Zhiyong Wei to be added to signature lists. Timeline to include production dates - ie include UAT and production roll-out dates. Dependencies - where there are …

  9. 19 Mar 2001

    Zhiyong Wei to Louise Kitchen and 10 more

    RE: GTV II

    Please see the attached file for the revised inception document. I would appreciate any comments. We will be working on the specification of phase 2 once this document is…

  10. 19 Mar 2001

    Louise Kitchen to Zhiyong Wei and 10 more

    RE: GTV II

    Comments: Zhiyong Wei to be added to signature lists. Timeline to include production dates - ie include UAT and production roll-out dates. Dependencies - where there are …

  11. 16 Mar 2001

    Zhiyong Wei to Louise Kitchen and 10 more

    RE: GTV II

    Louise, Attached please find the inception document requested. I would greatly appreciated your comments. I will be consulting Colleen and Geoff for any necessary revisio…

  12. 16 Mar 2001

    Zhiyong Wei to Louise Kitchen and 10 more

    RE: GTV II

    Louise, Attached please find the inception document requested. I would greatly appreciated your comments. I will be consulting Colleen and Geoff for any necessary revisio…

  13. 15 Mar 2001

    Cherylene Westbrook to Philippe A Bibi, Greg Piper, Jenny Rub and 46 more

    Beth Perlman - Out of Office

    Beth Perlman will be out of the office tomorrow 3/16 and the week of 3/19 - 3/23 for foot surgery and recovery. Beth will be home during this time and you can reach her a…

  14. 12 Mar 2001

    Colleen Sullivan to Zhiyong Wei, Geoff Storey, Karima Husain and 3 more

    2nd Revised Meeting Notes & NEXT MEETING

    There is one more addition to the Meeting Notes from last week. I overlooked the very important live feed for Gas Daily/intra-month curves, so the revised file below adds…

  15. 8 Mar 2001

    Zhiyong Wei to Colleen Sullivan and 6 more

    RE: REVISED MEETING NOTES

    Colleen, I didn't see the live-update of Gas Daily curves in your meeting notes. Should we add it? Please advise. Thanks Zhiyong

  16. 8 Mar 2001

    Colleen Sullivan to Zhiyong Wei, Karima Husain, Geoff Storey and 6 more

    REVISED MEETING NOTES

    Please see the attached revision to the meeting notes. You will see the change indicated in RED under Issue #2, Gas Daily. We want to put this item on HOLD for now becaus…

  17. 6 Mar 2001

    Colleen Sullivan to Geoff Storey, Stephen Stock, Zhiyong Wei

    IT/Gas Trading Meeting

    The meeting we discussed will be on Wednesday, March 7 at 3:00 pm in EB3267. Please feel free to bring whoever else you think is appropriate. Geoff will present the top p…

  18. 5 Mar 2001

    Vince J Kaminski to Stephen Stock and 2 more

    Re: Status

    Steve, Welcome back. Let's have coffee ASAP and review all the projects under way. Vince From: Stephen Stock/ENRON@enronXgate on 03/01/2001 09:40 AM To: Vince J Kaminski/…

  19. 2 Mar 2001

    Shirley McDowell to Jeffrey C Gossett, Kam Keiser, Darron C Giron and 6 more

    Trader Web-site Information

    Greetings All! As most of you know, there is a Trader Web-site project initiative currently in progress to identify specific reports that traders have produced every day …