  1. 27 Feb 2001

    Kenny Maltby to scott.jones@enron.com and 20 more

    Re: Rogas Line -- USFW Approval

    I received the proposed contract for both compensation credits and fees for EOTT and it's contractors to be put on Kern Water Banks Master Permit. Compensation credit wil…

  2. 26 Feb 2001

    Kenny Maltby to Edward Attanasio and 18 more

    Re: Rogas Line -- USFW Approval

    I just spoke with Cheryl Harding about getting the proposed contract for compensation credits. The NCL credits are for habitat disturbance only not incidental take. KWB c…

  3. 21 Feb 2001

    John.Shafer@enron.com to Kenny Maltby, scott.jones@enron.com and 20 more

    Re: Rogas Line -- USFW Approval

    Kenny and Scott, I agree with Ed's note concerning the need to move expeditiously in the purchase of compensation acreage noted by the US Fish and Wildlife Service (Servi…

  4. 21 Feb 2001

    Larry.Campbell@enron.com to John Shafer, scott.jones@enron.com and 20 more

    Re: Rogas Line -- USFW Approval

    John, Scott Jones, I believe is still on vacation in Hawaii of all places. And I believe you are correct that we have around 15 acres of existing credit. Kenny, let me kn…

  5. 20 Feb 2001

    Edward Attanasio to Kenny Maltby, scott.jones@enron.com and 16 more

    Rogas Line -- USFW Approval

    Randi McCormick just forwarded to me a letter addressed to EOTT, dated February 14, 2001 from the US Fish and Wildlife Service approving our project "for participation in…

  6. 19 Feb 2001

    Edward Attanasio to scott.jones@enron.com and 8 more

    Endangered Species Habitat Compensation Acreage

    I last week received word from the US BLM that Koch Oil failed to fulfill a condition in a right of way granted by the BLM in 1997. Specifically, Koch failed to procure 2…

  7. 12 Feb 2001

    Larry Campbell to John Shafer and 8 more

    Permitting Status, Rogas Construction Project

    John, this is a short note to let you know where we stand on the 7 mile pipeline construction Rogas Project with respect to environmental permitting and approvals. The fo…

  8. 8 Feb 2001

    John Shafer to Larry Campbell and 6 more

    Re: Annual Report

    Larry and Scott, I would suggest you do three things related to furnishing the Annual Report for 1999 and 2000 to the CDFG: (1) I would ask you to take it personnally to …

  9. 1 Feb 2001

    Larry Campbell to Edward Attanasio and 14 more

    Re: No. Coles Levee to Rogas Interconnect - Permit & Property Owner R equirements

    Ed the 6" project you are talking about is a small project independant of Rogas where a 6"line will be constructed from North Coles and run above ground, if possible, to …