with:ron.matthews@enron.com means Ron Matthews (ron.matthews@enron.com).
-
31 Aug 2001
Kevin Hyatt to Dennis Alters, Nancy Bagot, Larry Campbell and 30 more
Sun Devil Open Season Results --CONFIDENTIAL--
Overall, the results from Thursday's open season on our Sun Devil Project were very favorable (see below). Contract terms ranged from two to sixteen years. San Juan 84% s…
-
31 Aug 2001
Bryan Reinecke to Kevin Hyatt, Ron Matthews and 4 more
Sun Devil Project Comparisons To El Paso
Kevin, Here are some numbers for you to look at. I worked up three cases, one looking at a San Juan route, and two others looking at El Paso's Line 2000. The first Line 2…
-
31 Aug 2001
Doug Cebryk to Ron Matthews, Norm Spalding, Morgan Gottsponer and 9 more
RE: Sun Devil Pipeline Lengths
To All: I was very optimistic in my target of getting the Level B estimate ready by Sept 21. Based on the amount of work that will need to be done to get a decent +/- 10%…
-
30 Aug 2001
Ron Matthews to Norm Spalding, Morgan Gottsponer, John R. Keller and 7 more
RE: Sun Devil Pipeline Lengths
A preliminary model has been developed based on the limited information Doug, Kevin, and I discussed yesterday. A finished product won't be complete until such time as el…
-
30 Aug 2001
Morgan Gottsponer to John Sturn, Rich Jolly, David Roensch and 16 more
RE: La Plata DRA Conference Call - 9:00 CST, Friday, 8/31
For any Houston people who are interested, I've reserved 42C2 for this call. -Morgan
-
30 Aug 2001
John Sturn to Rich Jolly, David Roensch, Kimberly Watson and 17 more
La Plata DRA Conference Call - 9:00 CST, Friday, 8/31
The La Plata DRA conference call has been scheduled for 9:00 a.m., CST, Friday, 08/31. The dial in information is below. The purpose of the call is to review all we know …
-
29 Aug 2001
Doug Cebryk to Kevin Hyatt, Ron Matthews and 4 more
RE: Sun Devil Pipeline Lengths
Kevin I'll need to fly the routes and assess the terrain conditions. I plan to do this on Sept 11&12 Ron will need to run the hydraulics on the various options. We both t…
-
29 Aug 2001
Darrell Schoolcraft to John Sturn, Rich Jolly, David Roensch and 17 more
RE: La Plata to Bloomfield Drag Reducing Agent Conference Call
How does 9:00 work for everyone. This is a very critical topic and needs to be discussed asap. DS
-
29 Aug 2001
John Sturn to Rich Jolly, David Roensch, Kimberly Watson and 17 more
La Plata to Bloomfield Drag Reducing Agent Conference Call
Well, that didn't work. Neither Thursday nor Friday at 2:00 will work. I'll try one more time for this week. Please let me know by noon, Thursday if you can not make any …
-
22 Aug 2001
Ron Matthews to Kevin Hyatt, Morgan Gottsponer, Doug Cebryk and 4 more
Sun Devil Project - Level B Request "REVISED"
I found a mistake in the first Excel spreadsheet when discussing with Kim Kouri. Cost Estimate Summary sheet (2nd tab) did not add all of the rows down for the San Juan p…
-
21 Aug 2001
Ron Matthews to Kevin Hyatt, Morgan Gottsponer and 2 more
Sun Devil Project - Level B Request
Attached is a Level B request for the Sun Devil project. Keep in mind that this should include only right of way at this time. Details on the compression will probably ch…
-
20 Aug 2001
Ron Matthews to Kevin Hyatt, Morgan Gottsponer, Eric Faucheaux
Sun Devil Project
Attached is the latest and greatest breakdown of facilities and Level A costs related to Sun Devil. Facilities are not final and will be refined as the project unfolds.
-
20 Aug 2001
Susan Wadle to Sarah Haden, Michelle Lokay, Doug Cebryk and 17 more
Sun Devil Team introductory get together
Please join us for lunch from 11:30 to 12:30 on Wednesday, August 22 in the Executive Dining Room on 50M to meet other members of the team and discuss the project. RSVP b…
-
13 Aug 2001
Eric Faucheaux to Ron Matthews and 4 more
RE: Caithness - Big Sandy Project
They will also be required to sign a confidential, proprietary information form. This form is in the Supplement Section where you got the attachments in your original mes…
-
13 Aug 2001
Ron Matthews to ketchek@bp.com and 6 more
Caithness - Big Sandy Project
Attached are the engineering standards you requested on our latest telephone discussion with Kim Watson. Also attached is a cost estimate summary that the numbers were ma…