25 Mar 2002
Jerry Graves to Gary E. Anderson, ken.anderson@enron.com, judy.beck@enron.com and 37 more
Links Report Through December 2002
Please review the attached Links Report. (Note) Hugoton's final ESD plan will be finished soon. Hopefully by week's end. Jerry Graves 713-345-8923
-
21 Mar 2002
Jerry Graves to team.ashland@enron.com, team.beaver-mach-shop@enron.com, team.beaver-plant@enron.com and 118 more
Bushton Universe, DesMoines, and Dakota Region Outage Reports Through December 2002
Please review the attached outage report that pertains to your region. If you have any questions, please give me a call. Jerry Graves 713-345-8923 (Office) 713-646-2584 (…
-
21 Mar 2002
Jerry Graves to Lynn Blair, scott.clark@enron.com, Shelley Corman and 32 more
NNG Outage Weekly
The Outages attached below have some potential flow impact, or are points of interest. (NNG) Jerry Graves 713-345-8923
-
19 Mar 2002
Jerry Graves to Jesse Alvarado, ken.anderson@enron.com, Roy Armitage and 136 more
Amarillo, Beatrice, Midland, and Minneapolis Region Outage Reports Through December 2002
Please review the attached outage report that pertains to your region. If you have any questions, please give me a call. Jerry Graves 713-345-8923
-
19 Mar 2002
Jerry Graves to Gary E. Anderson, ken.anderson@enron.com, judy.beck@enron.com and 36 more
Links Report Through December 2002
Please review the attached Links Report. (Please note that the Hugoton team is still working on the final scope of work that will take place during their ESD (5/7/02). Th…
-
13 Mar 2002
Jerry Graves to c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com and 53 more
Outage Coordination Commercial Review Meeting (NNG)
FYI, The next Outage Coordination Commercial Review meeting is today, 03/13/02. The purpose for the meeting is to discuss outages that have a flow impact for the month of…
-
8 Mar 2002
Jerry Graves to c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com and 53 more
Outage Coordination Commercial Review Meeting (NNG)
FYI, The next Outage Coordination Commercial Review meeting is 03/13/02. The purpose for the meeting is to discuss outages that have a flow impact for the month of April …
-
8 Mar 2002
Jerry Graves to Lynn Blair, scott.clark@enron.com, Shelley Corman and 32 more
NNG Outage Weekly
The Outages attached below have some potential flow impact, or are points of interest. (NNG) Jerry Graves 713-345-8923