with:morgan.gottsponer@enron.com means Morgan Gottsponer (morgan.gottsponer@enron.com).
-
28 Sep 2001
Steven Harris to Teb Lokey, Audrey Robertson, Glen Hass and 6 more
RE: Pemex (MGI) Proposal
It is not intended to be a negotiated rate. We will add the other language when a definitive agreement is executed.
-
28 Sep 2001
Teb Lokey to Audrey Robertson, Steven Harris, Glen Hass and 6 more
RE: Pemex (MGI) Proposal
Is the intent that this will be a negotiated rate? If not, do we need to add language that the discounted rate will be between max and min rates? All else looks fine. -- …
-
28 Sep 2001
Lee Huber to Audrey Robertson, Steven Harris, Glen Hass and 6 more
RE: Pemex (MGI) Proposal
looks fine to me
-
28 Sep 2001
Audrey Robertson to Steven Harris, Glen Hass, Teb Lokey and 8 more
Pemex (MGI) Proposal
The following note is from Kim Watson: Please review the attached proposal for Pemex (MGI) for firm transportation on Transwestern. Please forward all comments back to St…
-
28 Sep 2001
Morgan Gottsponer to dl-ets_pfp@enron.com
ETS Planning Weekly Report
Attached is the weekly report for ETS Planning for the week ending September 28, 2001. Please call with any questions. Morgan Gottsponer
-
27 Sep 2001
Kimberly Watson to Mansoor Abdmoulaie, Morgan Gottsponer, Ron Matthews and 3 more
RE: TW/NNG & Sid Richardson
I've got it booked! Mark, please plan to attend with me. Thanks, Kim.
-
27 Sep 2001
Kimberly Watson to Stephen Herber, Mansoor Abdmoulaie and 4 more
RE: TW/NNG & Sid Richardson
I will be on vacation tomorrow through next week. I would be available pretty much anytime week of Oct. 8. Thanks, Kim.
-
27 Sep 2001
Mansoor Abdmoulaie to Kimberly Watson, Stephen Herber and 4 more
TW/NNG & Sid Richardson
Planning has met with ENA on Tuesday and responded to the questions from ENA. Let's four of us have a meeting in my office sometime next week and follow-up on this projec…
-
26 Sep 2001
Audrey Robertson to Audrey Robertson, Mansoor Abdmoulaie, Ben Asante and 57 more
RE: ETS' TW Teams Appreciation Luncheon - Last Round
If you have not responded, please do so by today. Thanks, Audrey D. Robertson Transwestern Pipeline Company email address: audrey.robertson@enron.com (713) 853-5849 (713)…
-
26 Sep 2001
Maurice Gilbert to Kevin Hyatt and 6 more
RE: Salt storage
Kevin: Thanks for the information and 5000 feet of halite if it is one uniform bed is certainly similar to Gulf Coast salt domal opportunities. If you decide to move forw…
-
25 Sep 2001
Ron Matthews to Kimberly Watson, Dennis Alters, Morgan Gottsponer and 2 more
Caithness Big Sandy Project
Kim, The attached file contains a recap of the Timberline program results with a few mods. Basic information covers what Earl and I talked about today. Caithness engineer…
-
20 Sep 2001
Audrey Robertson to Dennis Alters, Ben Asante, Ramona Betancourt and 31 more
FW: New Location for Steve Harris' Staff Meeting
Please be informed, Steve Harris and the TW Commercial Group will temporarily relocated to the 13th floor effective Monday, September 24, 2001. Our present meeting locati…
-
19 Sep 2001
Kimberly Watson to Steven Harris, Teb Lokey, Lee Huber and 3 more
Big Sandy Delivery Point Const and Oper Agreement
Please review the attached agreement for the Big Sandy Interconnect. It is very standard. It is reimbursable. It has a few blanks that have to be filled in for certain da…
-
19 Sep 2001
Audrey Robertson to Audrey Robertson, Mansoor Abdmoulaie, Ben Asante and 55 more
Rescheduled Appreciation Luncheon for ETS' TW Teams
We are pleased to announce the new date and time of our Appreciation Luncheon. Please mark your calendars for Thursday, September 27, 11:30a - 3:00p. We will meet at the …
-
18 Sep 2001
Kimberly Watson to Jo Williams, Morgan Gottsponer and 2 more
RE: Gray Interconnect
Jo, I actually mentioned this in our TW staff meeting with Steve yesterday about using the OBA's to balance this point for November service if the interconnect was not re…
-
14 Sep 2001
Eric Faucheaux to Lorraine Lindberg and 4 more
RE: EDG and Red Cedar
The work is completed and the project is closed. The figures that I saw indicated that the project was under budget where Red Cedar might be receiving some change. I thin…
-
10 Sep 2001
Kevin Hyatt to Dennis Alters, Nancy Bagot, Larry Campbell and 26 more
Yahoo - Transwestern Pipeline Announces Successful Open Season for Proposed Sun
http://biz.yahoo.com/prnews/010910/dam046_1.html
-
10 Sep 2001
Jerry Graves to c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com and 77 more
Outage Coordination Commercial Review (Date Change)
FYI, Please take note of the date change. The next Outage Coordination Commercial Review meeting is 09/13/01. The purpose for the meeting is to discuss outages that have …
-
7 Sep 2001
Ron Matthews to Kevin Hyatt and 4 more
Ssun Devil Expansion Project - Level A Estimate
Attached is the scope and Level A cost estimate for the above mentioned project. This is the same package given to Engineering for them to prepare their Level B. Ron M.
-
4 Sep 2001
Eric Faucheaux to Kimberly Watson and 4 more
Calpine Cost Estimates
I spoke with Earl regarding the cost differences indicated for the Calpine -Topock interconnect. The project files were discarded when the E&C Group moved to 3 Allen Cent…