with:mark.walker@enron.com means Mark V Walker (mark.walker@enron.com).
-
28 Jun 2002
Patricia Hunter to Mark V Walker and 6 more
Re: New 6.1 Version of SPLUS will be shipped soon.
We have the new software. Rabi will load SPlus and Oracle on his and my system to make sure he does not encounter any problems with the new GE Core Load. Once our test is…
-
28 Jun 2002
Mark V Walker to Patricia Hunter, Rabi Sahoo and 4 more
New 6.1 Version of SPLUS will be shipped soon.
FYI, a new version of SPLUS is coming. I've been coordinating with Tech Support at Insightful about some erratic or erroneous behaviour in timeDate data. One problem whic…
-
27 Jun 2002
Joe Chapman to Mark V Walker and 8 more
Operating State 29
Mark, The operating state codes 2 to 6 represent manual pitch overide. The user can issue these pitch overides from the "Control blade angle" screen as shown in Figure-1.…
-
27 Jun 2002
Mark V Walker to Jeff Duff and 2 more
Re: Total Down Time
What definition of down time do you mean? If the GEWE definition, the time when the turbine is faulted off automatically or in a repair status, is used then yes your are …
-
27 Jun 2002
Jeff Duff to Mark V Walker, Mark Fisher
Total Down Time
As a verification of understanding; Total Down Time = TO - (DT + RT +LOT + MT + EST + WOT) Where TO = Total possible survey time. Thanks, Jeff
-
27 Jun 2002
Mark V Walker to Joe Chapman, Garth Ripton and 2 more
Operating State 29
Joe Chapman sent us an email listing a short textual description associated with each value of Operating State 29. Some are easy to interpret (ex. 11 is "Feathering posit…
-
27 Jun 2002
Mark V Walker to Jeff Duff and 2 more
Re: Availability forecasting and related $ liability
Jeff Duff 06/27/2002 07:07 AM To: Mark V Walker/EWC/Enron@ENRON cc: Subject: Re: Availability forecasting and related $ liability Mark, Please send me a copy of this repo…
-
26 Jun 2002
John M Ruiz to Matt Allsup, ronda.foster@enron.com, richard.soles@enron.com and 18 more
VisuPro data for June 2002
Please be advised. The VisuPro download to cd for June SCADA data should be done on Monday, July 1 and sent to Tehachapi as "Next Day Delivery." The files needed for mont…
-
26 Jun 2002
Jeff Duff to julie.johnson@enron.com and 8 more
Work request
Julie, Could you print off the current work request report by 1:30 today? Gentlemen, I'd like to review this today at 1:30 in our office. Also, could you provide me with …
-
20 Jun 2002
Jeff Duff to Mark V Walker, Mark Fisher
Definition of Availability
Gents, I was asked to provide the following information along with the data I will be sending and taking with me next week. Could you also please advise re. the following…
-
19 Jun 2002
Jeri Fish to jerry.holt@enron.com, naomi.brown@enron.com, John Nemila and 59 more
SIX SIGMA
Ladies and Gentlemen, Many of you have received the Six Sigma Green Belt Training CD. If you have not, contact your supervisor or Jeri Fish to obtain a copy. All salaried…
-
19 Jun 2002
Jeff Duff to Mark Fisher, Mark V Walker
STAR Lite
Here is a copy of the spec doc I've put together. It is not as comprehensive as I'd like, but should give you an idea of the capabilities. Any input would be great. JD
-
18 Jun 2002
Hollis Kimbrough to Mark V Walker, Mark Fisher, Jeff Duff and 4 more
6 Sigma CDs
Everyone, Please let me know if you have a 6 Sigma CD or not. The company has one for everyone but there are no extras so it important that you all have one but not two. …
-
18 Jun 2002
Kevin Cousineau to Hollis Kimbrough, Mark V Walker, Mark Fisher
Meter Readings
Guys: Attached are the meter readings for Indian Mesa for both feeders (transformers). They includ the production and the cumsumption, and cover a period between May 19 a…
-
17 Jun 2002
Mark V Walker to Kurt Anderson, Joe Thorpe and 2 more
Status of Timeslices from discussion with Zilka.
On Friday Joe said that he would send us the timeslices of pause mode events and any PMT breaker operations that were brought up by Verkleeren or that were presented to V…
-
17 Jun 2002
Mark V Walker to John M Ruiz, Jeff Duff, Mark Fisher and 3 more
Six Sigma Pitch
The attached Powerpoint slide file gives the high level overview of the Six Sigma program as it will be applied at GEWE. The comments I'll give you this afternoon are in …
-
17 Jun 2002
Jeff Duff to Mark V Walker, Mark Fisher, Matthew Meyers and 2 more
Green belt six sigma debrief
Let's meet today at 1:30 in our office for a quick debrief on the green belt six sigma debrief and pass out your green belt disk. Also, please bring copies of your weekly…
-
17 Jun 2002
Jeff Maurer to Kurt Anderson, Hollis Kimbrough and 10 more
Re: CPS curtailment meeting
Hollis, In your absence, I have decided to appoint Jeff Duff to meet in San Antonio with AEP and CPS to go over curtailment calculation. He will review and familiarize hi…
-
17 Jun 2002
Joe Thorpe to Kurt Anderson, Mark Fisher, Hollis Kimbrough and 5 more
Meeting with Gary
Kurt, As requested here is a brief overview of the discussion between Mark Fisher , myself and Gary Verklereen that took place on 6/13/02 & 6/14/02 regarding availability…
-
14 Jun 2002
John M Ruiz to Mark V Walker and 2 more
Re: Visupro Status As of 6/12/02 10:00 hrs
FYI, Fenner Turbine 17 mon0205: There is a gap occuring for this turbine from 5/16 to 5/21 approximate I have downloaded Mon files from Fenner using VisuPro remote. And i…
-
14 Jun 2002
Kurt Anderson to Hollis Kimbrough and 10 more
CPS curtailment meeting
Hollis, we need to determine who from GEWE will attend this meeting. Please discuss this issue with Jeff Maurer on Monday and make the necessary arrangements. On Monday A…
-
14 Jun 2002
Kurt Anderson to Tim Mohammed and 10 more
Re: Zilkha Availability
First off I want to thank all for their involvement and assistance in addressing Zilkha's concerns regarding our availability calcs at Mill Run Somerset. The customer is …
-
14 Jun 2002
Tim Mohammed to Mark V Walker, Kevin Cousineau and 8 more
Re: Zilkha Availability
Mark, How would the generator run if the PMT breaker tripped? Normally, CB1 will trip for undervolatge due to lose of power. Thanks
-
14 Jun 2002
Mark V Walker to Tim Mohammed and 8 more
Re: Zilkha Availability
To cut to the chase....would CB1 fault the turbine when the PMT breaker tripped and if so then would the downtime or line out time availability hour counter be incremente…
-
14 Jun 2002
Tim Mohammed to Joe Thorpe and 16 more
Zilkha Availability
Joe, Lets not forget that we had measure problems due to failing MS3 relay in the SEG converter, which caused the crow bar to engage, which in turn forced CB1 to fault. C…