with:lhand@lemle.com means Lawrence J. Hand, Jr." @ENRON (lhand@lemle.com).
-
27 Dec 2000
Jr. Lawrence J. Hand to Gerald Nemec
RE: Bridgeline Storage Co. 24 " pipeline
thanks for the info. i'll get it filed with time to spare. this matter will be heard on 1/18/2001 and we will need a witness. we can address the hearing/witness later. th…
-
27 Dec 2000
Gerald Nemec to Lawrence J. Hand, Jr." @ENRON and 4 more
Bridgeline Storage Co. 24 " pipeline
Larry, I am OK with the form and Robert's changes, except that the proper name is Bridgeline Storage Company, LLC. No periods after the LLC. Everything else looks fine.
-
12 Dec 2000
Jr. Lawrence J. Hand to gnemec@ect.enron.com, Rusty Belflower, robert.d.morgan@bhlp.com
Bridgeline Storage Co. 24 " pipeline
Gentlemen: enclosed is a draft application to the Louisiana Office of Conservation for authority to construct and operate pipeline facilities. Please let me know if you h…
-
12 Dec 2000
Gerald Nemec to Lawrence J. Hand, Jr." @ENRON and 4 more
Re: 24" pipeline project - Bridgeline Storage
Larry, I am working with Robert Morgan to get the proper approvals at Bridgeline and I will insure that the proper approvals are obtained from Enron. "Lawrence J. Hand, J…
-
12 Dec 2000
Jr. Lawrence J. Hand to Shonnie Daniel, gnemec@ect.enron.com and 2 more
24" pipeline project - Bridgeline Storage
I have received all needed engineering information from Rusty Belflower, with the exception of an area map which will be provided. The application is essentially complete…
-
11 Dec 2000
Amy L. Baird to Rusty Belflower and 6 more
RE: 24" Pipeline Description
Excellent. I feel like the Maytag repairman.
-
8 Dec 2000
Rusty Belflower to Lawrence J. Hand, Jr." @ENRON and 8 more
Re: 24" pipeline project
I believe the following should be used. Robert please concur. 1875 psi should be used for the MAOP in both cases. Completion date should be 06-30-2001. It is outside of c…
-
8 Dec 2000
Jr. Lawrence J. Hand to Rusty Belflower and 6 more
24" pipeline project
enclosed is a draft application to construct and operate the 24" pipeline extension to Enron Brine No. 1 Well. Please provide me with any comments. <<Application for Auth…
-
8 Dec 2000
Rusty Belflower to Amy L. Baird and 6 more
24" Pipeline Description
Please comment on this "Draft" description to be used for the permit application for the pipeline connecting the new storage well with the compression facility. The pipel…