with:jan.moore@enron.com means Jan Moore (jan.moore@enron.com).
-
28 Feb 2002
Jerry Graves to Jesse Alvarado, Roy Armitage, team.artesia@enron.com and 72 more
Albuquerque Region Outage report Through December 2002
Please review the attached outage report. Jerry Graves 713-345-8923 (Office) 713-646-2584 (Fax)
-
28 Feb 2002
Michelle Lokay to TK Lohman and 2 more
FW: Rates for New/Extended Contracts
Western #27834 is .095 (one-part plus fuel), and Western #27835 should only be for 5,000 not 10,000 and is at a rate of .13 (one-part plus fuel). Oneok is correct at roll…
-
28 Feb 2002
Jan Moore to Lorraine Lindberg, Michelle Lokay, TK Lohman and 2 more
Rates for New/Extended Contracts
Could you please get with T.K. and have her put in the appropriate rates in CBS for the following contracts: CR # Shipper Effective MDQ 27834 WGR 4/1/02 - 10/31/02 5,000 …
-
28 Feb 2002
Craig Buehler to Craig Buehler, Esther Dasilva, Dennis Lee and 17 more
TW Contract Status as of February 28th @ 10 am
PROCESSING None... TENDERED 02-062 Questar Eff 1/1/02 Interconnect & Operating K EXECUTED 25374 Oneok Extend to 3/31/02 12,000/d Panhdle to Beav #1 EXECUTED 26471 PPL Eff…
-
28 Feb 2002
Craig Buehler to Craig Buehler, Esther Dasilva, Dennis Lee and 17 more
TW Contract Status as of February 28th @ 9:30 am
PROCESSING None... TENDERED 02-062 Questar Eff 1/1/02 Interconnect & Operating K EXECUTED 25374 Oneok Extend to 3/31/02 12,000/d Panhdle to Beav #1 EXECUTED 26471 PPL Eff…
-
28 Feb 2002
Craig Buehler to Craig Buehler, Esther Dasilva, Dennis Lee and 17 more
TW Contract Status as of February 28th @ 8:50 am
PROCESSING 26758 Duke Eff 3/1-3/31/02 40,000/d Swap RP Vol Processing 27496 Reliant Extend to 3/31/02 30,000/d SJ Pool to Blmfld Processing TENDERED 02-062 Questar Eff 1/…
-
27 Feb 2002
Jan Moore to Darrell Schoolcraft
Commodity Impact of La Plata Outage
Darrell: Would you PLEASE go into the CAS system and let me know what shippers have primary firm at these three points: NWPL La Plata POI #500533 WFS Ignacio POI #500535 …
-
27 Feb 2002
Craig Buehler to Craig Buehler, Esther Dasilva, Dennis Lee and 17 more
TW Contract Status as of February 27th @ 1:10 pm
PROCESSING None TENDERED 02-062 Questar Eff 1/1/02 Interconnect & Operating K EXECUTED 25374 Oneok Extend to 3/31/02 12,000/d Panhdle to Beav #1 EXECUTED 26471 PPL Eff RR…
-
27 Feb 2002
Michael Bodnar to Jan Moore, Richard Hanagriff and 12 more
PNR thru Feb 27th
Summary of Activity.... Buyer PO# POI Dekatherm Rate/Dth Rate_Type Invoice Amount Astra Power 27502 500621 7,216 $0.0500 Total $432.96 USGT 27268 500617 20,000 $0.0800 To…
-
27 Feb 2002
Historical Average Rates
I tried to find the original spreadsheet that I'm sure you sent me where you calculated these quarterly rates, but I can't find it. Do you recall these rates? My question…
-
27 Feb 2002
Craig Buehler to Craig Buehler, Esther Dasilva, Dennis Lee and 17 more
TW Contract Status as of February 27th @ 10:35 am
PROCESSING Sempra 3/1-3/31/02(LFT) 15,000/d Blmfld to Southwest Processing TENDERED 02-062 Questar Eff 1/1/02 Interconnect & Operating K EXECUTED 25374 Oneok Extend to 3/…
-
27 Feb 2002
TK Lohman to Vincent Strohmeyer, Debbie Moseley, Jan Moore and 4 more
Confirmations
Please find attached REVISED confirmations for 2/27/02 and 2/26/02. Thanks, TK
-
26 Feb 2002
Craig Buehler to Craig Buehler, Esther Dasilva, Dennis Lee and 17 more
TW Contract Status as of February 26th @11:15 am
PROCESSING None TENDERED 02-062 Questar Eff 1/1/02 Interconnect & Operating K EXECUTED 25374 Oneok Extend to 3/31/02 12,000/d Panhdle to Beav #1 EXECUTED 26471 PPL Eff RR…
-
26 Feb 2002
Craig Buehler to Craig Buehler, Esther Dasilva, Dennis Lee and 17 more
TW Contract Status as of February 26th @10 am
PROCESSING None TENDERED 02-062 Questar Eff 1/1/02 Interconnect & Operating K EXECUTED 25374 Oneok Extend to 3/31/02 12,000/d Panhdle to Beav #1 Tendered 2/26 26471 PPL E…
-
26 Feb 2002
-
26 Feb 2002
Jan Moore to Lindy Donoho, Gina Taylor
RE: TW 2001 Throughput
1.8 Bcf is the average of actual throughput per day.
-
26 Feb 2002
Lindy Donoho to Gina Taylor, Jan Moore
RE: TW 2001 Throughput
That's what I was asking Jan previously - does the 1.8 Bcf/d include any estimates or is that an actual number? Gina, I am waiting for Steve to respond to two e:mails I'v…
-
26 Feb 2002
Gina Taylor to Lindy Donoho, Jan Moore
RE: TW 2001 Throughput
Thanks! Should I call an estimate or is this actual? Also, any changes on the slide I sent yesterday? Gina
-
26 Feb 2002
Lindy Donoho to Gina Taylor, Jan Moore
RE: TW 2001 Throughput
I have 1.8 Bcf/d for annual daily average for total system in 2001 on TW.
-
26 Feb 2002
Gina Taylor to Lindy Donoho, Jan Moore
RE: TW 2001 Throughput
I'll take an estimate for TW througput per day. I need something in the next hour, if possible. Thanks for immediate attention....Gina
-
26 Feb 2002
FW: TW - feb 28 2002 bank presentation north american assets.ppt
Jan, What percentage of our revenues from from demand charges in 2001? Gina has a bullet here that says "over 90%". Is this in the ballpark?
-
26 Feb 2002
Lindy Donoho to Jan Moore and 2 more
TW 2001 Throughput
Jan, I had a number from you for one of the presentations we put together, but I wasn't sure if it was the final, actuals for 2001. What was TW's total actual throughput …
-
26 Feb 2002
TK Lohman to Vincent Strohmeyer, Debbie Moseley, Jan Moore and 3 more
Confirmation
Please find attached confirmation for Astra.
-
26 Feb 2002
TK Lohman to Vincent Strohmeyer, Debbie Moseley, Jan Moore and 3 more
Confirmations
Please find attached confirmations for Tenaska and Richardson. There still may be a confirmation coming for Astra. Thanks, TK
-
26 Feb 2002
Craig Buehler to Craig Buehler, Esther Dasilva, Dennis Lee and 17 more
TW Contract Status as of February 26th @ 8:30 am
PROCESSING 25374 Oneok Extend to 3/31/02 12,000/d Panhdle to Beav #1 Processing TENDERED 02-062 Questar Eff 1/1/02 Interconnect & Operating K EXECUTED 26471 PPL Eff RR In…