with:hollis.kimbrough@enron.com means Hollis Kimbrough (hollis.kimbrough@enron.com).
-
19 Jun 2002
Jeri Fish to jerry.holt@enron.com, naomi.brown@enron.com, John Nemila and 59 more
SIX SIGMA
Ladies and Gentlemen, Many of you have received the Six Sigma Green Belt Training CD. If you have not, contact your supervisor or Jeri Fish to obtain a copy. All salaried…
-
19 Jun 2002
Hollis Kimbrough to Mark Fisher
Old VG SPC Results - Question
Mark, Turbine 5 (the prototype I think) shows up on some graphs but not on all graphs. Do you know why this is occurring? HK
-
19 Jun 2002
-
19 Jun 2002
-
19 Jun 2002
-
19 Jun 2002
Hollis Kimbrough to elliott.fong@enron.com, mike.lewis@enron.com and 12 more
Old VG SPC Results
Attached please find a new Statistical Process Control analytic which displays the turbine performance for your site. The report pdf is a summary of the other two reports…
-
19 Jun 2002
Hollis Kimbrough to alden.zeitz@enron.com and 12 more
750 SPC Analytic
Attached please find a new Statistical Process Control analytic which displays the turbine performance for your site. The report pdf is a summary of the other two reports…
-
19 Jun 2002
-
19 Jun 2002
Hollis Kimbrough to Mark Fisher
Re: WR569 SPC report (750)
Mark, This is great! Would you send me copies for all the sites? Thanks, Hollis
-
18 Jun 2002
Ronald Brzezinski to Mark Fisher and 10 more
Re: Questions/Observations about VisuPro
Mark, I'd like to expand on Kevin's explanation: - Time-stamping: If the owner wants Standard time all year and have a 1 hour offset for half the year, that is his decisi…
-
18 Jun 2002
Hollis Kimbrough to Mark V Walker, Mark Fisher, Jeff Duff and 4 more
6 Sigma CDs
Everyone, Please let me know if you have a 6 Sigma CD or not. The company has one for everyone but there are no extras so it important that you all have one but not two. …
-
18 Jun 2002
Kevin Cousineau to Hollis Kimbrough, Mark V Walker, Mark Fisher
Meter Readings
Guys: Attached are the meter readings for Indian Mesa for both feeders (transformers). They includ the production and the cumsumption, and cover a period between May 19 a…
-
18 Jun 2002
Kevin Cousineau to Mark Fisher and 8 more
Re: Questions/Observations about VisuPro
Mark: First, the new version of VisuPro (Version IV) will use standard local time, not daylight time. This means that during the year it will be off by one hour for 1/2 o…
-
17 Jun 2002
Mark V Walker to John M Ruiz, Jeff Duff, Mark Fisher and 3 more
Six Sigma Pitch
The attached Powerpoint slide file gives the high level overview of the Six Sigma program as it will be applied at GEWE. The comments I'll give you this afternoon are in …
-
17 Jun 2002
Jeff Maurer to Kurt Anderson, Hollis Kimbrough and 10 more
Re: CPS curtailment meeting
Hollis, In your absence, I have decided to appoint Jeff Duff to meet in San Antonio with AEP and CPS to go over curtailment calculation. He will review and familiarize hi…
-
17 Jun 2002
Joe Thorpe to Kurt Anderson, Mark Fisher, Hollis Kimbrough and 5 more
Meeting with Gary
Kurt, As requested here is a brief overview of the discussion between Mark Fisher , myself and Gary Verklereen that took place on 6/13/02 & 6/14/02 regarding availability…
-
14 Jun 2002
Kurt Anderson to Hollis Kimbrough and 10 more
CPS curtailment meeting
Hollis, we need to determine who from GEWE will attend this meeting. Please discuss this issue with Jeff Maurer on Monday and make the necessary arrangements. On Monday A…
-
14 Jun 2002
Kurt Anderson to Tim Mohammed and 10 more
Re: Zilkha Availability
First off I want to thank all for their involvement and assistance in addressing Zilkha's concerns regarding our availability calcs at Mill Run Somerset. The customer is …
-
14 Jun 2002
Tim Mohammed to Mark V Walker, Kevin Cousineau and 8 more
Re: Zilkha Availability
Mark, How would the generator run if the PMT breaker tripped? Normally, CB1 will trip for undervolatge due to lose of power. Thanks
-
14 Jun 2002
Mark V Walker to Tim Mohammed and 8 more
Re: Zilkha Availability
To cut to the chase....would CB1 fault the turbine when the PMT breaker tripped and if so then would the downtime or line out time availability hour counter be incremente…
-
14 Jun 2002
Tim Mohammed to Joe Thorpe and 16 more
Zilkha Availability
Joe, Lets not forget that we had measure problems due to failing MS3 relay in the SEG converter, which caused the crow bar to engage, which in turn forced CB1 to fault. C…
-
13 Jun 2002
Joe Thorpe to Kurt Anderson, Kevin Cousineau, Tim Mohammed and 10 more
Zilkha Availability
Kurt, Per our phone conversation, Mark Fisher and myself have been discussing availability with Gary from Zilkha. A question arose regarding the many operations of our br…
-
13 Jun 2002
Shirley Peters to pat.weaver@enron.com, norm.phillips@enron.com, phil.waddell@enron.com and 50 more
Fax Number 661.823.6752
FYI - Fax number 661.823.6752 will change tomorrow 06/14/02 to 661.823.6428. I do not have a definite time that this change will happen tomorrow, but it will take place s…
-
11 Jun 2002
Hollis Kimbrough to Matthew Meyers and 12 more
Re: Cost Center?
Matthew, Our new cost center is cc 269. This was effective at the beginning of the year. Regards, Hollis
-
10 Jun 2002