  1. 29 May 2002

    Jeff Duff to Mark Fisher, Mark V Walker, David Miller and 10 more

    Re: STARlite Update

    Please see the attached STARlite project update. JD

  2. 29 May 2002

    Kurt Anderson to Benjamin Bell and 16 more

    Re: FW: GEWE reporting and follow-up

    Ben, Rick Winsor's note below has prompted me to provide a timeline with regards to the issue of Zilka's concerns with our Availability calculations. 5/2/02 Rick Winsor s…

  3. 28 May 2002

    Mark V Walker to Kurt Anderson and 6 more

    Re: Desert Sky

    The contractual availability definition in the owner report is the same used throughout 2002 and implements the contractual availability definition upon which annual avai…

  4. 27 May 2002

    Benjamin Bell to lois.woodland@enron.com and 12 more

    Re: FW: GEWE reporting and follow-up

    Lois: Please schedule a meeting this week (preferably late Tues or Weds) with the cc'ed group above and help coordinate a conference call with Rick Winsor at Zilkha towar…

  5. 27 May 2002

    Benjamin Bell to michael@zilkha.com and 22 more

    Re: FW: GEWE reporting and follow-up

    Dear Michael, We, too, enjoyed the opportunity to meet with you last Thursday and appreciate the candid feedback you and Michael were able to give us regarding the PA pro…

  6. 24 May 2002

    Jeff Duff to David Miller, Patricia Hunter and 8 more

    DB Table Additions

    To support the data storage of ZMET data here is a proposal for what the table structure should be. In addition, after discussing the status messages it is important to d…

  7. 22 May 2002

    Ronald Brzezinski to rec-scada@enron.com, Mark Fisher and 8 more

    Re: Spannungswerte USA

    Klaus, I spoke with Hollis. He sounds fine. He is not sure when he will be back to work. They still do not know exactly what happened. I spoke with Mark Fisher. He is in …

  8. 22 May 2002

    Ronald Brzezinski to Klaus Holtel, Mark Fisher and 8 more

    Re: Spannungswerte USA

    Klaus, I spoke with Hollis. He sounds fine. He is not sure when he will be back to work. They still do not know exactly what happened. I spoke with Mark Fisher. He is in …

  9. 20 May 2002

    Nagwa Elkachouty to Mark Fisher and 2 more

    Re: Trent Mesa Gen/Temp data

    Mark; good set of data, please proceed. I shall work with this set of data for now and see later if we need to get anything else. thanks nagwa

  10. 20 May 2002

    Hollis Kimbrough to Ilan Caplan and 6 more

    "Vestas Availability"

    Ilan, Per your request here is the VA with the leaning towers removed and the 90 day ramp up also removed. Discounting the leaning towers, there is a slight variation (ge…

  11. 20 May 2002

    Matt Allsup to Kurt Anderson and 6 more

    Desert Sky Curtailment April 2002

    ---------------------- Forwarded by Matt Allsup/EWC/Enron on 05/20/2002 11:10 AM --------------------------- Matt Allsup 05/20/2002 08:41 AM To: Kurt Anderson/EWC/Enron@E…

  12. 20 May 2002

    Matt Allsup to Kurt Anderson and 6 more

    Desert Sky Curtailment April 2002

    Kurt, I have attached the April Log with some corrections to the curtailments. The lines I shaded blue are typing errors that I fixed. These will account for the negative…

  13. 20 May 2002

    Hollis Kimbrough to Mark Fisher

    Work Request

    Mark, Please see attached, Thanks, Hollis

  14. 20 May 2002

    Hollis Kimbrough to Mark Fisher

    Re: "Vestas Availability"

    Mark, Let's discuss. Hollis

  15. 17 May 2002

    Hollis Kimbrough to Mark Fisher

    Re: Vestas non-leaning

    Are the leaning towers excluded for both EA and VA? Did we also exclude the turbines within the 90 day ramp up? HK

  16. 17 May 2002

    Hollis Kimbrough to ruth.meyer@enron.com and 4 more

    Summarized Counter Values

    Ruth, We have had a request from our commercial group for turbine availability numbers with the availability as defined by Vestas. The purpose of this is to present a cha…

  17. 17 May 2002

    Hollis Kimbrough to Ilan Caplan and 6 more

    Re: April Availability

    Ilan, In order to calculate the VA we need the actual VisuPro counter data since we are using an assumed formula for the Vestas Availability. (See attached for this year …

  18. 17 May 2002

    Ronald Brzezinski to Mark Fisher and 4 more

    Trent ATP data

    Mark, Jimmy Chandler has sent the ATP data files and hard-copy data sheets to you via FedEx. You should be receiving these Monday. Jimmy made an extra CD for SCADA engine…

  19. 15 May 2002

    Hollis Kimbrough to Kevin Cousineau

    Sampling Model

    Kevin, In my previous e-mail I said the sampling frequency will affect the final result when it comes to calculating payment for consumed power. I have modeled the impact…

  20. 15 May 2002

    Hollis Kimbrough to Ilan Caplan

    Re: Vestas Availability 2002

    Ilan, 1. We have not received the European data yet. 2. The data does include the first 90 days in both the EA and the VA. We can exclude the first 90 days if that is des…

  21. 15 May 2002

    Hollis Kimbrough to Ilan Caplan, Benjamin Bell and 8 more

    Vestas Availability 2002

    Ilan, Here is our first attempt at a "Vestas Availability" calculation. We did this for the US 1.5 fleet for each month in the year 2002. There are some things you should…

  22. 15 May 2002

    Hollis Kimbrough to Jeff Duff, Mark V Walker, Mark Fisher and 1 more

    WHITEWATER - LOCATION & FACILITIES FOR SERVICE CREW

    fyi... It is great news to be starting new projects! HK

  23. 15 May 2002
  24. 15 May 2002

    Hollis Kimbrough to Kevin Cousineau and 6 more

    Re: Consumption for for GE1.5

    Kevin, We routinely prepare that data and it is available for all our turbines. The problem is that the consumption/production is a net number for a 5.5 minute period so …

  25. 15 May 2002

    Mark V Walker to Hollis Kimbrough and 4 more

    Re: Calculating "Vestas Availability"

    For clarification, the "Vestas availability" you talk about is not specific to Vestas nor is it based on any Vestas contractual availability. This availability is a multi…