  1. 23 Jan 2002

    Doug Cebryk to Kevin Hyatt and 2 more

    RE: FERC application cost for Sun Devil

    Kevin As we discussed today, since we don't know anymore today than we did when we made the original estimate, you can assume this is still a good estimate to take it to …

  2. 23 Jan 2002

    Kevin Hyatt to Doug Cebryk and 2 more

    FERC application cost for Sun Devil

    Doug-- We are working up a proposal for APS in Phoenix wherein they would share in a portion of the costs we incur to get the project's FERC application ready. Tab 5 of t…

  3. 16 Jan 2002

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 13 more

    weekly Sun Devil update meeting

    We've changed the weekly scheduled meeting to accommodate more people's calendars: When: every Tuesday When: 3pm Where: 15c1

  4. 14 Jan 2002

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 9 more

    Sun Devil update moved to tues 1/15

    due to Conf room conflict (Ken Lay needed our room!). We'll do it on Tues at 3:30 in 15c1. We'll update you on the Phoenix meetings last week plus the Desert Crossing pro…

  5. 14 Jan 2002

    Kevin Hyatt to Doug Cebryk

    FW: Needles Golf Tournament

    -----Original Message----- From: Roensch, David Sent: Monday, January 14, 2002 1:04 PM To: Harris, Steven; Watson, Kimberly; Hyatt, Kevin Cc: Kingman-Needles, Team Subjec…

  6. 7 Jan 2002

    Doug Cebryk to Ron Matthews, Arnold L. Eisenstein, Dennis Alters and 7 more

    RE: Sun Devil Alterative - Revision #10

    Ron I will be out of the office Jan 9 - 11 inclusive for personal reasons. E&C will be working on the new estimate in my absence and we will likely be able to provide you…

  7. 7 Jan 2002

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 11 more

    Sun Devil Update moved to Tues 3:30 pm 15c1

    this change is for today only as I have a meeting conflict on another project. Let me know please if you can't make it. We have some interesting developments to discuss i…

  8. 7 Jan 2002

    Ron Matthews to marcello.minotti@enron.com, Arnold L. Eisenstein, Doug Cebryk and 2 more

    Sun Devil Design Conditions

    Sorry I left the above out of the first email. Attached is the latest and greatest taken from Winflow. There is a possibility of elimianting Bloomfield unit #5 but don't …

  9. 7 Jan 2002

    Ron Matthews to Doug Cebryk, Arnold L. Eisenstein, Dennis Alters and 3 more

    Sun Devil Alterative - Revision #10

    Attached is a revised scope which basically includes the majority of the expansion volume to Phoenix. Only 30 MMcf/d goes west of Station #2 while 500 MMcf/d goes to Phoe…