with:brian.gillis@enron.com means Brian Gillis (brian.gillis@enron.com).
-
30 Sep 2001
Phillip M. Love to Jeffrey C. Gossett, Brian Gillis
RE: FYI - the NGI-MICH_CG for Sep appears not to have been pub-posted.
I have never heard of this location. I only see a basis and index curve for this, no intra month, Storey has this location in his curve file. We have no deals at this loc…
-
28 Sep 2001
Bob Ambrocik to aaron.adams@enron.com, ana.agudelo@enron.com, Billie Akhave and 821 more
Solar Migration - Very Important
During the weekend of October 6 and 7, 2001 the Enterprise Storage Team will be migrating all production users off the current hardware (Solar) that houses their home and…
-
27 Sep 2001
Truong Vu to richard.cross@enron.com, Jeffrey C. Gossett, Francis S. Lim and 66 more
MLK and Presidents Days from 2002 to 2025 removed
Richard, I removed Martin Luther King's Day and Presidents' Day as business days from test, stage and production databases. Below are the list of days. Truong Vu x 5-3416…
-
18 Sep 2001
Mechelle Atwood to Wes Colwell, Sally Beck, Rob Milnthorp and 13 more
Canada Trading Audit Report
The Canada Trading Audit, executed by Andersen, has been completed. The attached Final Report has been reviewed with key process owners and issues were discussed with app…
-
17 Sep 2001
Tom Victorio to Chris Abel, Kristin Albrecht, Beth Apollo and 33 more
Agenda for 8:30 AM Tuesday Risk Meeting
Agenda for 8:30 AM Tuesday Risk Meeting EB2831, 713-646-3638 Daily officialization status Process around re-officialization RiskTrac hierarchy maintenance If you have sug…
-
17 Sep 2001
Margie Nguyen to Chris Abel, thomas.araujo@enron.com, David Baumbach and 85 more
Correction: Curve Load with Tibco
Please note the correction in red below Thanks
-
17 Sep 2001
Margie Nguyen to Chris Abel, thomas.araujo@enron.com, David Baumbach and 85 more
Curve Load with Tibco
Hi all, There has been a problem some of us have had with a Curve Load excel file. This curve load file was not developed by TAGG/ERMS. Therefore, to resolve this problem…
-
12 Sep 2001
Shona Wilson to Shona Wilson, Sally Beck, Brent A. Price and 20 more
Updated: Curve validation - rescheduled meeting
I've checked your calendars and this time looks good for most of you. Please let me know if you can attend. We don't have a room scheduled yet, we'll let you know as soon…
-
11 Sep 2001
Tom Victorio to Chris Abel, Kristin Albrecht, Beth Apollo and 33 more
Agenda for 8:30 Risk Meeting - EB2831
Risk Group Meeting, 8:30AM Tuesday EB2831 Dial-in # 713-646-3638 Agenda: 8:30 - 8:50: Daily officialization status 8:50 - 9:30: Update on Book archiving process Update on…
-
7 Sep 2001
Francis S. Lim to Chris Abel, thomas.araujo@enron.com, David Baumbach and 131 more
Please read: ERMT migration to 8i
All, As you are aware that the ERMT database will be migrated to Oracle 8i on Saturday, September 15. In order to start the process, TAGG/ERMS will be unavailable from 8 …