from:shona.wilson@enron.com means Shona Wilson (shona.wilson@enron.com).
to:ted.murphy@enron.com means Ted Murphy (ted.murphy@enron.com).
-
28 Dec 2001
Shona Wilson to Chris Abel, Naveen Andrews, Beth Apollo and 83 more
RE: DPR reporting - update on timing
The preliminary should be out by the end of the day on the 2nd of January, not the 1st as noted below. Sorry for the confusion. Regards
-
28 Dec 2001
Shona Wilson to Chris Abel, Naveen Andrews, Beth Apollo and 83 more
DPR reporting
Plans for the reporting of the consolidated DPR are: For trading date Friday, December 28th - No DPR For trading date Monday, December 31st - Our goal is to publish this …
-
12 Dec 2001
Shona Wilson to Chris Abel, Naveen Andrews, Beth Apollo and 53 more
status update on the DPR
We have postponed issuing the DPR until the terminations that have already been entered into are appropriately reflected in the risk books. My aim is to produce a full pr…
-
11 Dec 2001
Shona Wilson to Chris Abel, Naveen Andrews, Beth Apollo and 55 more
update on issuance of the DPR
The DPR for 11/30/01 is now complete and has been published to the ERV. For the last few days, the production of the DPR has been put on hold due to the increased activit…
-
5 Dec 2001
Shona Wilson to darrell.aguilar@enron.com, Patricia Anderson, Naveen Andrews and 63 more
11/30 and 12/3 DPR - update as of 12/15/01
For the next few days, we will be reporting only positions, maturity gap, & VAR for the DPR. We expect to be reporting P&L for ENA again probably by the middle of next we…
-
4 Dec 2001
Shona Wilson to Chris Abel, darrell.aguilar@enron.com, Patricia Anderson and 68 more
11/30 and 12/3 DPR - update
With all of the events of yesterday, information for the DPR for the above dates is not yet complete. At the present time, we are planning to issue a final DPR for the 30…
-
22 May 2001
Shona Wilson to Brent A. Price, Debbie R. Brackett, David W Delainey and 35 more
DPR by commodity
We have designed an additional Daily Position Report which consolidates P&L, positions, maturity gap, and VAR by commodity rather than business unit. In accordance with t…
-
2 May 2001
Shona Wilson to Beth Apollo, Sally Beck, Rick Buy and 7 more
4/30/01 UK Power DPR loss
The UK Power 5 day rolling loss of $29,475K noted in the April 30, 2001preliminary DPR is not considered a limit notification because that number includes $11 million of …
-
24 Apr 2001
Shona Wilson to Rick Buy, Ted Murphy, David Port and 7 more
4/20 Americas gas VAR limit violation
Attached is the Enron Americas gas VAR limit violation for April 20, 2001. The head trader for Enron Americas is responsible for printing out a hard copy of this memo, si…
-
6 Mar 2001
Shona Wilson to John J Lavorato, John Sherriff, Jeffrey A Shankman and 26 more
merchant asset reclass in DPR
We have been asked to reclassify the Merchant Assets on the DPR. Currently, these assets are shown below the total trading line of the DPR, because, as per the risk polic…
-
31 Jan 2001
Shona Wilson to Cassandra Schultz and 14 more
Re: Sales Agency Arrangements
Further information - during the NY doorstep we noted that this issue as it relates to agents used by North America has been cleared, with the exception of one S. Korea a…
-
18 Jan 2001
Shona Wilson to philip.bacon@enron.com, joe.robertson@enron.com, Marcelo Parra and 22 more
NY Doorstep
Dear Phil, Joe, & Marcelo, I wanted to drop you a line on behalf of your doorstep visitors to let you know we appreciate the time, effort, and cooperation the NY, St Loui…
-
16 Jan 2001
Shona Wilson to Ted Murphy, Sally Beck, Bjorn Hagelmann and 2 more
NY Doorstep with Word Stuff
Draft report for tomorrow. We have cleared the findings with Mike Jordan, Marcelo Parra, and Lou Colarusso, and will clear the report with them after we discuss it tomorr…
-
15 Dec 2000
Shona Wilson to Ted Murphy and 10 more
Re: Dec 13 DPR
Dear John, The following are the amounts that make up the $5.8 mil. I have looked into your query and noted that there was a late adjustment not exported to us (so not ca…
-
21 Nov 2000
Shona Wilson to Jeffrey C Gossett, Stacey W White, Leslie Reeves and 40 more
Holiday daily position report reporting
Due to the Thanksgiving Holiday in the U.S., the NYMEX and equity markets will be closed on Thursday the 23rd and the NYMEX will be closed on Friday the 24th. The consoli…
-
14 Nov 2000
Shona Wilson to David Maxwell and 24 more
Re: Enron Raptor I P&L Reversal
The change to the DPR will occur on the 14th, not on the 13th as previously communicated. Best regards Shona Wilson X39123 From: David Maxwell @ ECT 11/13/2000 03:24 PM T…
-
9 Nov 2000
Shona Wilson to Andrew Cornfield and 14 more
Re: Authorised Traders : Montreal & Chicago
Dear Andy, Thanks for the e-mail. What does internally mean? To: Bjorn Hagelmann/HOU/ECT@ECT cc: Sally Beck/HOU/ECT@ECT, Ted Murphy/HOU/ECT@ECT, Shona Wilson/NA/Enron@Enr…
-
9 Nov 2000
Shona Wilson to Bjorn Hagelmann and 10 more
Re: Authorized Traders : Montreal & Chicago
I'll talk to Marcelo, but if they can't implement the appropriate control structure, then they have to be shut. To: Sally Beck/HOU/ECT@ECT, Shona Wilson/NA/Enron@Enron, T…
-
3 Nov 2000
Shona Wilson to Tim Poullain-Patterson and 16 more
Re: Chicago Doorstep Review
Dear Tim, Thanks for the info. We have followed up on all points noted in the first review and have found a couple more. We will want to discuss these on Monday. I should…
-
17 Oct 2000
Shona Wilson to Sally Beck, Ted Murphy, Cassandra Schultz
MG Future structure
I found a more updated version than the one I sent you yesterday. Best regards
-
16 Oct 2000
Shona Wilson to Ted Murphy, Sally Beck, Cassandra Schultz
Re: action point list
Here is the list Marcelo and I put together in September (see attachment at the bottom).
-
16 Oct 2000
Shona Wilson to Ted Murphy, Sally Beck and 2 more
latest MG integration plan
The plan looks good - but is not fully implemented. I've left a message with Marcelo to get an update on what the status is. I'll fill you in once we've talked. Regards
-
5 Oct 2000
Shona Wilson to Rick L Carson and 10 more
Re: updates to processes
Dear Rick, Thanks for the update. I appreciate your input as I do not know what your discussions with Rick Buy have been. To address your points below: 1) I agree that yo…
-
20 Sep 2000
Shona Wilson to Ted Murphy, Sally Beck, Rick L Carson and 4 more
updated doorstep budget
After our discussion yesterday, I've updated the doorstep budget. I'm working on the schedule (starting 9/2000) and hope to get that to you soon as well. Best regards Sho…
-
19 Sep 2000
Shona Wilson to David Maxwell and 4 more
Re: Genoil addition to MPR
We need to schedule a Calgary visit in the next couple weeks to let them know what we expect of them. Ted - do you have someone from RAC you could send with us? From: Dav…